Backfill material (flowable fill) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $443.59 per CY for item 204-08.01, backfill material (flowable fill), over the 24 months to 02 OCT 2026, across 34 low bids. Half of all 110 bids fell between $390.50 and $550.00.
- Owner
- Tennessee DOT
- Item
- 204-08.01
- Unit
- CY
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 4 | 4 | $338.00 | 13 | $313.56 |
| 2020 | 5 | 5 | $226.00 | 22 | $301.50 |
| 2023 | 3 | 3 | $250.00 | 12 | $294.50 |
| 2024 | 22 | 22 | $425.00 | 70 | $412.47 |
| 2025 | 9 | 9 | $400.00 | 32 | $425.00 |
| 2026 | 15 | 15 | $462.17 | 50 | $441.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 2 to 9 | 8 | $527.00 |
| 10 to 15 | 9 | $400.00 |
| 20 to 47 | 8 | $450.00 |
| 57 to 200 | 9 | $400.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261074 | Claiborne County | 47 | $500.00 | $453.56 | 4 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 9 | $425.00 | $425.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 125 | $472.30 | $472.30 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 10 | $900.00 | $900.00 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN264052 | Tipton County | 12 | $400.00 | $530.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 6 | $580.00 | $515.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 188 | $275.00 | $333.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 15 | $585.00 | $585.20 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN263052 | Maury County | 5 | $400.00 | $428.50 | 8 | Eubank Asphalt Paving & Sealing, LLC | TDOT |
| 26 JUN 2026 | CN261044 | Monroe County | 99 | $990.00 | $459.16 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 12 | $580.00 | $462.50 | 4 | Civil Constructors, LLC | TDOT |
| 08 MAY 2026 | CN264033 | Gibson County | 15 | $400.00 | $328.10 | 2 | Delta Contracting Company, LLC | TDOT |
| 08 MAY 2026 | CN264039 | Henderson County | 25 | $400.00 | $400.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 08 MAY 2026 | CN264036 | Henry County | 10 | $400.00 | $425.00 | 4 | Delta Contracting Company, LLC | TDOT |
| 06 FEB 2026 | CN261011 | Sevier County | 128 | $462.17 | $462.17 | 1 | Charles Blalock & Sons, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.