Sediment removal unit price, Tennessee
Low bidders on TDOT contracts carried a median of $33.00 per CY for item 209-05, sediment removal, over the 24 months to 02 OCT 2026, across 125 low bids. Half of all 417 bids fell between $20.00 and $60.00.
- Owner
- Tennessee DOT
- Item
- 209-05
- Unit
- CY
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 17 | 17 | $15.00 | 58 | $31.18 |
| 2019 | 1 | 1 | $37.00 | 4 | $24.00 |
| 2020 | 12 | 11 | $28.96 | 40 | $23.35 |
| 2023 | 6 | 6 | $80.00 | 18 | $58.75 |
| 2024 | 66 | 65 | $33.00 | 204 | $30.00 |
| 2025 | 51 | 51 | $38.00 | 168 | $35.93 |
| 2026 | 43 | 43 | $30.00 | 159 | $32.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 5 | $23.91 | 23 | $23.91 |
| Shelby County | 7 | $35.00 | 21 | $35.00 |
| Sumner County | 4 | $48.02 | 17 | $33.50 |
| Cumberland County | 4 | $24.20 | 16 | $24.83 |
| Williamson County | 3 | $30.00 | 14 | $30.00 |
| Hamilton County | 4 | $47.25 | 13 | $80.00 |
| Humphreys County | 3 | $40.00 | 12 | $38.75 |
| Anderson County | 3 | $15.00 | 12 | $15.38 |
| Bradley County | 3 | $37.29 | 12 | $49.36 |
| Campbell County | 4 | $58.50 | 10 | $50.50 |
| Gibson County | 3 | $30.00 | 10 | $31.00 |
| Sullivan County | 4 | $40.33 | 10 | $40.73 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 27 | 31 | $67.31 |
| 28 to 68 | 31 | $40.00 |
| 68 to 200 | 31 | $30.00 |
| 222 to 21,734 | 32 | $20.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261076 | Anderson County | 14 | $85.00 | $62.50 | 4 | Rogers Group, Inc. | TDOT |
| 02 OCT 2026 | CN263064 | Bedford County | 17 | $30.00 | $30.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN261070 | Carter County | 2 | $90.00 | $95.00 | 3 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 54 | $50.00 | $41.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261069 | Cocke County | 59 | $100.23 | $70.00 | 4 | Whaley Construction, LLC | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 302 | $9.00 | $15.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 92 | $100.00 | $33.48 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 66 | $40.00 | $37.16 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 421 | $30.00 | $47.50 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 650 | $40.65 | $40.65 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 50 | $66.00 | $27.50 | 4 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 44 | $20.00 | $24.60 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 4,699 | $12.14 | $18.40 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 255 | $20.00 | $20.00 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 170 | $40.00 | $40.00 | 5 | Mack Construction, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.