Temporary silt fence (with backing) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $6.00 per LF for item 209-08.02, temporary silt fence (with backing), over the 24 months to 02 OCT 2026, across 109 low bids. Half of all 388 bids fell between $5.24 and $7.00.
- Owner
- Tennessee DOT
- Item
- 209-08.02
- Unit
- LF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 12 | 12 | $4.75 | 38 | $5.00 |
| 2019 | 1 | 1 | $4.50 | 4 | $7.65 |
| 2020 | 13 | 13 | $4.50 | 50 | $4.50 |
| 2023 | 7 | 7 | $7.59 | 24 | $8.04 |
| 2024 | 56 | 56 | $6.38 | 186 | $6.22 |
| 2025 | 45 | 45 | $6.21 | 154 | $6.05 |
| 2026 | 40 | 40 | $5.50 | 157 | $5.89 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Sumner County | 3 | $4.01 | 16 | $5.12 |
| Cumberland County | 4 | $5.93 | 16 | $5.00 |
| Rutherford County | 4 | $6.36 | 15 | $6.00 |
| Coffee County | 3 | $4.90 | 13 | $5.40 |
| Humphreys County | 4 | $4.70 | 13 | $5.00 |
| Anderson County | 3 | $5.50 | 12 | $6.38 |
| Hamilton County | 3 | $5.25 | 12 | $6.39 |
| Shelby County | 4 | $6.00 | 11 | $6.50 |
| Hawkins County | 3 | $7.00 | 9 | $6.98 |
| Carter County | 3 | $14.00 | 9 | $13.00 |
| Sullivan County | 3 | $7.00 | 7 | $10.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 55 to 592 | 27 | $6.47 |
| 670 to 1,593 | 27 | $6.50 |
| 1,599 to 4,220 | 27 | $5.70 |
| 4,436 to 228,555 | 28 | $5.44 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN263064 | Bedford County | 450 | $5.90 | $5.95 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN261070 | Carter County | 742 | $14.00 | $13.00 | 3 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261067 | Carter County | 300 | $27.00 | $15.86 | 4 | Eclipse Companies,LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 592 | $6.00 | $6.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 4,436 | $5.50 | $6.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 1,240 | $10.00 | $6.98 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 2,378 | $4.60 | $5.05 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 700 | $7.01 | $7.01 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 19,000 | $6.52 | $6.52 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 7,318 | $4.00 | $4.98 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 129,857 | $4.46 | $4.67 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 3,200 | $5.25 | $5.25 | 5 | Mack Construction, LLC | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 860 | $4.73 | $6.03 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN262060 | Meigs County | 2,500 | $5.42 | $5.77 | 5 | Mid-State Construction Company, Inc. | TDOT |
| 14 AUG 2026 | CN264054 | Shelby County | 10,040 | $5.50 | $5.78 | 2 | Dement Construction Group, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way