Rock check dam unit price, Tennessee
Low bidders on TDOT contracts carried a median of $833.00 per EACH for item 209-08.07, rock check dam, over the 24 months to 02 OCT 2026, across 66 low bids. Half of all 223 bids fell between $692.22 and $1,110.83.
- Owner
- Tennessee DOT
- Item
- 209-08.07
- Unit
- EACH
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2023 | 1 | 1 | $660.00 | 2 | $742.50 |
| 2024 | 36 | 36 | $825.00 | 117 | $820.00 |
| 2025 | 26 | 26 | $913.16 | 84 | $928.14 |
| 2026 | 23 | 23 | $761.25 | 87 | $890.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 3 | $800.00 | 14 | $850.00 |
| Bradley County | 3 | $1,100.00 | 12 | $1,175.00 |
| Shelby County | 4 | $1,274.39 | 11 | $1,623.78 |
| Hamilton County | 3 | $1,198.33 | 9 | $1,198.33 |
| Hawkins County | 3 | $1,200.00 | 9 | $1,000.00 |
| Sullivan County | 3 | $740.70 | 6 | $695.35 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 4 | 16 | $1,099.16 |
| 4 to 9 | 17 | $875.00 |
| 10 to 36 | 16 | $925.66 |
| 36 to 706 | 17 | $650.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN264057 | Hardin County | 10 | $1,000.00 | $1,000.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 10 | $1,200.00 | $1,000.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 6 | $500.00 | $810.00 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 100 | $740.70 | $740.70 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 18 | $375.00 | $600.00 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 4 | $800.00 | $750.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 706 | $761.25 | $825.00 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 6 | $840.00 | $920.00 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264054 | Shelby County | 4 | $2,200.00 | $1,925.00 | 2 | Dement Construction Group, LLC | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 91 | $750.00 | $750.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 36 | $694.44 | $953.68 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN261901 | Johnson County | 2 | $2,000.00 | $1,479.58 | 2 | Southern Constructors, Inc. | TDOT |
| 26 JUN 2026 | CN264037 | Lake County | 20 | $900.00 | $900.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN263052 | Maury County | 9 | $500.00 | $750.00 | 8 | Eubank Asphalt Paving & Sealing, LLC | TDOT |
| 26 JUN 2026 | CN261044 | Monroe County | 410 | $577.50 | $623.25 | 6 | Charles Blalock & Sons, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way