Curb inlet protection (type 4) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $382.91 per EACH for item 209-09.43, curb inlet protection (type 4), over the 24 months to 02 OCT 2026, across 25 low bids. Half of all 74 bids fell between $170.31 and $424.75.
- Owner
- Tennessee DOT
- Item
- 209-09.43
- Unit
- EACH
- Latest letting
- 26 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 4 | 4 | $341.00 | 10 | $163.12 |
| 2020 | 6 | 6 | $262.50 | 18 | $200.00 |
| 2024 | 15 | 15 | $350.00 | 40 | $320.52 |
| 2025 | 12 | 12 | $391.46 | 34 | $360.00 |
| 2026 | 6 | 6 | $356.45 | 20 | $277.45 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 2 to 7 | 6 | $437.50 |
| 8 to 17 | 6 | $372.75 |
| 20 to 87 | 6 | $400.00 |
| 112 to 256 | 7 | $312.90 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 JUN 2026 | CN264903 | Dyer County | 7 | $425.00 | $475.00 | 2 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN264049 | Dyer County | 20 | $400.00 | $350.00 | 3 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 256 | $143.00 | $141.00 | 4 | Civil Constructors, LLC | TDOT |
| 26 JUN 2026 | CN263055 | Williamson County | 15 | $242.00 | $176.00 | 5 | Bell & Associates Construction, LLC | TDOT |
| 08 MAY 2026 | CN261040 | Knox County | 6 | $450.00 | $450.00 | 5 | Jamison Construction, LLC | TDOT |
| 06 FEB 2026 | CN261011 | Sevier County | 112 | $312.90 | $312.90 | 1 | Charles Blalock & Sons, Inc. | TDOT |
| 05 DEC 2025 | CNZ276 | Sullivan County | 231 | $550.00 | $446.30 | 2 | Nicholas Overbay DBA East Tennessee Turf and Landscape | TDOT |
| 03 OCT 2025 | CNZ278 | Carter County | 2 | $700.00 | $584.00 | 2 | Southern Constructors, Inc. | TDOT |
| 03 OCT 2025 | CNZ267 | Hamilton County | 17 | $375.50 | $399.75 | 2 | Dement Construction Group, LLC | TDOT |
| 15 AUG 2025 | CNZ903 | Unicoi County | 13 | $370.00 | $735.00 | 2 | Summers-Taylor, Inc. | TDOT |
| 15 AUG 2025 | CNZ213 | Hawkins County | 5 | $1,000.00 | $772.00 | 2 | Southern Constructors, Inc. | TDOT |
| 15 AUG 2025 | CNZ221 | Sumner County | 39 | $279.41 | $195.63 | 6 | Scotty's Contracting & Stone, LLC | TDOT |
| 27 JUN 2025 | CNZ194 | Benton County | 87 | $450.00 | $400.00 | 4 | Vaughn Contractors, Inc. | TDOT |
| 27 JUN 2025 | CNZ182 | Crockett County | 24 | $450.00 | $450.00 | 3 | Hal Coffey Contracting LLC | TDOT |
| 27 JUN 2025 | CNZ193 | Rutherford County | 14 | $140.00 | $229.40 | 4 | Capital City Construction Services, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.