Enhanced rock check dam unit price, Tennessee
Low bidders on TDOT contracts carried a median of $1,028.00 per EACH for item 209-08.08, enhanced rock check dam, over the 24 months to 02 OCT 2026, across 100 low bids. Half of all 345 bids fell between $850.00 and $1,450.00.
- Owner
- Tennessee DOT
- Item
- 209-08.08
- Unit
- EACH
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 9 | 9 | $700.00 | 33 | $500.00 |
| 2019 | 1 | 1 | $1,000.00 | 4 | $1,875.00 |
| 2020 | 9 | 9 | $512.74 | 34 | $625.00 |
| 2023 | 3 | 3 | $1,120.00 | 6 | $1,247.50 |
| 2024 | 48 | 48 | $1,000.00 | 152 | $1,045.00 |
| 2025 | 38 | 38 | $1,001.00 | 134 | $1,045.25 |
| 2026 | 37 | 37 | $1,032.86 | 138 | $1,080.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 4 | $863.16 | 19 | $926.32 |
| Sumner County | 3 | $698.31 | 16 | $847.00 |
| Cumberland County | 4 | $991.75 | 16 | $1,033.75 |
| Humphreys County | 3 | $1,150.00 | 12 | $1,250.00 |
| Anderson County | 3 | $1,250.00 | 12 | $1,175.00 |
| Sullivan County | 4 | $1,679.82 | 10 | $1,161.22 |
| Chester County | 3 | $1,800.00 | 8 | $1,175.00 |
| Shelby County | 3 | $2,212.15 | 8 | $1,670.00 |
| Hamilton County | 3 | $1,675.00 | 7 | $1,675.00 |
| Dyer County | 3 | $1,100.00 | 6 | $941.43 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3 | 25 | $1,270.00 |
| 3 to 6 | 25 | $1,150.00 |
| 7 to 13 | 25 | $1,000.00 |
| 13 to 295 | 25 | $997.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN263064 | Bedford County | 8 | $700.00 | $850.00 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 4 | $1,150.00 | $1,260.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 13 | $1,500.00 | $1,500.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 9 | $1,500.00 | $1,395.47 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 1 | $1,000.00 | $1,594.11 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 4 | $1,800.00 | $1,800.00 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 3 | $500.00 | $1,080.00 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 12 | $1,359.63 | $1,359.63 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 1 | $875.00 | $874.22 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 11 | $1,000.00 | $900.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 142 | $997.50 | $1,033.75 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 26 | $1,200.00 | $1,200.00 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 4 | $775.00 | $1,062.50 | 5 | Mack Construction, LLC | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 3 | $1,260.00 | $1,259.20 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN262060 | Meigs County | 7 | $922.24 | $982.55 | 5 | Mid-State Construction Company, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.