Changeable message sign unit unit price, Tennessee
Low bidders on TDOT contracts carried a median of $5,900.00 per EACH for item 713-16.01, changeable message sign unit, over the 24 months to 02 OCT 2026, across 260 low bids. Half of all 730 bids fell between $5,000.00 and $7,850.00.
- Owner
- Tennessee DOT
- Item
- 713-16.01
- Unit
- EACH
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 21 | 21 | $5,350.00 | 65 | $5,703.48 |
| 2020 | 24 | 23 | $6,210.00 | 69 | $6,500.00 |
| 2023 | 27 | 27 | $8,500.00 | 65 | $9,000.00 |
| 2024 | 107 | 106 | $6,064.50 | 273 | $6,240.00 |
| 2025 | 133 | 133 | $6,000.00 | 365 | $6,225.00 |
| 2026 | 88 | 87 | $5,069.00 | 260 | $5,300.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Shelby County | 14 | $5,178.58 | 44 | $5,077.24 |
| Rutherford County | 9 | $5,750.00 | 37 | $6,000.00 |
| Davidson County | 12 | $4,695.20 | 37 | $5,350.00 |
| Cumberland County | 13 | $5,330.00 | 34 | $6,000.00 |
| Coffee County | 7 | $6,079.00 | 24 | $6,171.65 |
| Knox County | 6 | $5,990.00 | 24 | $6,312.50 |
| Williamson County | 6 | $4,997.50 | 24 | $5,303.53 |
| Hamilton County | 11 | $5,600.00 | 22 | $6,000.00 |
| Sumner County | 6 | $5,850.00 | 20 | $7,971.60 |
| Bradley County | 7 | $5,052.63 | 20 | $5,775.00 |
| Maury County | 5 | $4,000.00 | 20 | $5,122.50 |
| Sullivan County | 8 | $7,250.00 | 19 | $7,500.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 65 | $6,095.00 |
| 2 to 3 | 65 | $5,067.00 |
| 3 to 4 | 65 | $6,100.00 |
| 4 to 21 | 65 | $5,900.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261074 | Claiborne County | 4 | $8,000.00 | $7,700.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 2 | $5,000.00 | $5,000.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 1 | $5,000.00 | $5,000.00 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261073 | Knox County | 2 | $5,000.00 | $7,630.00 | 4 | Bluegrass Contracting Corporation | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 10 | $4,985.00 | $5,365.00 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 2 | $11,030 | $11,030 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 4 | $5,495.00 | $5,607.14 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 8 | $12,600 | $12,950 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 4 | $6,000.00 | $6,300.00 | 5 | Mack Construction, LLC | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 2 | $5,500.00 | $8,500.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 4 | $5,300.00 | $6,250.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN264049 | Dyer County | 8 | $2,500.00 | $5,500.00 | 3 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN262047 | Fentress County | 2 | $4,000.00 | $3,750.00 | 2 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN262054 | Franklin County | 2 | $4,280.00 | $4,280.00 | 1 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN262048 | Grundy County | 2 | $6,000.00 | $6,000.00 | 1 | Rogers Group, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way