Low bidders on TDOT contracts carried a median of $41.00 per EACH for item 716-01.22, snowplowable raised pavment markers (mono-dir)(1 color), over the 24 months to 02 OCT 2026, across 212 low bids. Half of all 567 bids fell between $36.80 and $49.45.
- Owner
- Tennessee DOT
- Item
- 716-01.22
- Unit
- EACH
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 22 | 22 | $27.75 | 62 | $30.00 |
| 2023 | 3 | 3 | $186.02 | 8 | $168.01 |
| 2024 | 84 | 84 | $39.50 | 232 | $39.55 |
| 2025 | 106 | 106 | $41.00 | 283 | $41.00 |
| 2026 | 84 | 84 | $41.60 | 221 | $42.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Davidson County | 10 | $35.00 | 33 | $35.00 |
| Knox County | 9 | $40.00 | 30 | $40.00 |
| Williamson County | 6 | $35.00 | 29 | $40.22 |
| Maury County | 7 | $42.00 | 29 | $40.00 |
| Shelby County | 10 | $50.75 | 26 | $52.19 |
| Rutherford County | 6 | $41.20 | 24 | $40.55 |
| Cumberland County | 6 | $41.62 | 17 | $42.25 |
| Sumner County | 5 | $39.50 | 15 | $37.00 |
| Hamilton County | 8 | $43.10 | 15 | $43.70 |
| Monroe County | 4 | $41.50 | 14 | $42.50 |
| Coffee County | 4 | $36.00 | 13 | $60.00 |
| Hardin County | 4 | $44.00 | 12 | $48.48 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 4 to 32 | 53 | $44.00 |
| 33 to 106 | 53 | $41.00 |
| 106 to 296 | 53 | $40.50 |
| 300 to 2,093 | 53 | $41.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN264057 | Hardin County | 10 | $62.00 | $67.20 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 310 | $38.00 | $38.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 15 | $77.60 | $77.60 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 40 | $37.00 | $65.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 18 | $46.73 | $48.36 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 13 | $100.00 | $100.00 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 30 | $42.00 | $46.11 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN263048 | Bedford County | 8 | $35.00 | $35.00 | 4 | Hawkins Asphalt Paving, LLC | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 10 | $52.00 | $52.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 84 | $40.00 | $47.15 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN261054 | Greene County | 21 | $40.00 | $40.00 | 1 | Summers-Taylor, Inc. | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 32 | $44.00 | $46.95 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN264045 | Haywood County | 105 | $50.00 | $47.50 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN261056 | Knox County | 230 | $38.00 | $42.00 | 3 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN263052 | Maury County | 10.64 | $50.00 | $46.80 | 8 | Eubank Asphalt Paving & Sealing, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.