Extruded aluminum panel signs unit price, Tennessee
Low bidders on TDOT contracts carried a median of $31.00 per SF for item 713-14, extruded aluminum panel signs, over the 24 months to 02 OCT 2026, across 29 low bids. Half of all 90 bids fell between $30.00 and $35.91.
- Owner
- Tennessee DOT
- Item
- 713-14
- Unit
- SF
- Latest letting
- 14 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 3 | 3 | $40.00 | 10 | $33.40 |
| 2020 | 6 | 6 | $22.00 | 18 | $22.52 |
| 2023 | 1 | 1 | $31.10 | 5 | $31.10 |
| 2024 | 18 | 18 | $28.93 | 51 | $32.19 |
| 2025 | 11 | 11 | $31.00 | 34 | $32.00 |
| 2026 | 10 | 10 | $30.88 | 32 | $33.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 15 to 96 | 7 | $35.00 |
| 104 to 173 | 7 | $33.00 |
| 224 to 1,504 | 7 | $28.50 |
| 2,250 to 4,800 | 8 | $29.69 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 14 AUG 2026 | CN264048 | Dyer County | 15 | $35.00 | $35.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 40 | $28.04 | $44.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN261044 | Monroe County | 96 | $45.12 | $34.11 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 115 | $33.80 | $33.27 | 4 | Civil Constructors, LLC | TDOT |
| 08 MAY 2026 | CN261029 | Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington | 4,500 | $29.00 | $33.00 | 3 | Superior Traffic Control, LLC | TDOT |
| 08 MAY 2026 | CN263038 | Counties Bedford, Cheatham, Davidson, Dickson, Giles, Hickman, Houston, Humphreys, Lawrence, Lewis, Lincoln, Macon, Marshall, Maury, Montgomery, Moore, Perry, Robertson, Rutherford, Smith, Stewart, Sumner, Trousdale, Wayne, Williamson, And Wilson | 2,250 | $28.24 | $28.50 | 3 | Superior Traffic Control, LLC | TDOT |
| 08 MAY 2026 | CN264032 | Counties Benton, Carroll, Chester, Crockett, Decatur, Dyer, Fayette, Gibson, Hardeman, Hardin, Haywood, Henderson, Henry, Lake, Lauderdale, Madison, Mcnairy, Obion, Shelby, Tipton, And Weakley | 4,800 | $30.38 | $40.60 | 2 | Superior Traffic Control, LLC | TDOT |
| 08 MAY 2026 | CN262038 | Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And White | 3,000 | $33.00 | $33.00 | 3 | Superior Traffic Control, LLC | TDOT |
| 08 MAY 2026 | CN264039 | Henderson County | 737 | $30.75 | $30.75 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 08 MAY 2026 | CN264036 | Henry County | 90 | $31.00 | $31.00 | 4 | Delta Contracting Company, LLC | TDOT |
| 03 OCT 2025 | CNZ267 | Hamilton County | 40 | $37.89 | $34.75 | 2 | Dement Construction Group, LLC | TDOT |
| 15 AUG 2025 | CNZ206 | Cumberland County | 112 | $32.20 | $32.10 | 4 | Mid-State Construction Company, Inc. | TDOT |
| 15 AUG 2025 | CNZ221 | Sumner County | 532 | $32.00 | $34.59 | 6 | Scotty's Contracting & Stone, LLC | TDOT |
| 27 JUN 2025 | CNZ194 | Benton County | 312 | $28.04 | $39.02 | 4 | Vaughn Contractors, Inc. | TDOT |
| 27 JUN 2025 | CNZ193 | Rutherford County | 928 | $28.43 | $32.92 | 4 | Capital City Construction Services, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.