Concrete curb unit price, Tennessee
Low bidders on TDOT contracts carried a median of $1,029.62 per CY for item 702-01, concrete curb, over the 24 months to 02 OCT 2026, across 52 low bids. Half of all 132 bids fell between $882.50 and $1,600.00.
- Owner
- Tennessee DOT
- Item
- 702-01
- Unit
- CY
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 9 | 9 | $562.46 | 25 | $562.46 |
| 2020 | 6 | 6 | $777.50 | 13 | $745.00 |
| 2023 | 1 | 1 | $670.00 | 5 | $670.00 |
| 2024 | 27 | 27 | $1,040.00 | 74 | $1,200.00 |
| 2025 | 18 | 18 | $975.00 | 48 | $976.00 |
| 2026 | 17 | 17 | $1,034.25 | 38 | $1,079.62 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3 | 13 | $2,000.00 |
| 3 to 10 | 13 | $1,490.00 |
| 10 to 30 | 13 | $900.00 |
| 37 to 224 | 13 | $875.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261064 | Sullivan County | 60 | $767.62 | $767.62 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 27 | $1,034.25 | $1,079.62 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264052 | Tipton County | 51 | $885.00 | $1,067.50 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264903 | Dyer County | 60 | $1,170.00 | $1,047.50 | 2 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN264049 | Dyer County | 3 | $1,466.38 | $1,425.07 | 3 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN264045 | Haywood County | 1.30 | $900.00 | $1,170.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 69 | $869.00 | $855.50 | 4 | Civil Constructors, LLC | TDOT |
| 08 MAY 2026 | CN264033 | Gibson County | 55 | $875.00 | $834.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 20 MAR 2026 | CN263026 | Davidson County | 3 | $900.00 | $900.00 | 2 | Vulcan Construction Materials, LLC | TDOT |
| 20 MAR 2026 | CN261016 | Grainger County | 6 | $1,600.00 | $1,452.50 | 2 | PRI of East Tennessee Inc. | TDOT |
| 20 MAR 2026 | CN262024 | Hamilton County | 1 | $3,000.00 | $2,750.00 | 2 | APAC-Atlantic, Inc. | TDOT |
| 20 MAR 2026 | CN261023 | Knox County | 1 | $1,750.00 | $1,850.00 | 3 | PRI of East Tennessee Inc. | TDOT |
| 20 MAR 2026 | CN264022 | Obion County | 2.60 | $2,150.00 | $2,150.00 | 1 | Ford Construction Company | TDOT |
| 20 MAR 2026 | CN261024 | Sevier County | 1 | $2,000.00 | $4,977.67 | 2 | PRI of East Tennessee Inc. | TDOT |
| 20 MAR 2026 | CN264023 | Weakley County | 1.30 | $2,200.00 | $1,462.50 | 2 | Ford Construction Company | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.