Concrete curb ramp unit price, Tennessee
Low bidders on TDOT contracts carried a median of $30.00 per SF for item 701-02.03, concrete curb ramp, over the 24 months to 02 OCT 2026, across 37 low bids. Half of all 99 bids fell between $22.95 and $45.34.
- Owner
- Tennessee DOT
- Item
- 701-02.03
- Unit
- SF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 9 | 9 | $22.00 | 18 | $21.27 |
| 2020 | 5 | 5 | $31.75 | 12 | $26.73 |
| 2023 | 2 | 2 | $39.12 | 8 | $41.00 |
| 2024 | 21 | 21 | $32.00 | 56 | $33.00 |
| 2025 | 16 | 16 | $27.68 | 45 | $28.00 |
| 2026 | 9 | 9 | $45.69 | 18 | $42.84 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 3 | $25.00 | 13 | $27.70 |
| Hamilton County | 4 | $51.88 | 8 | $55.48 |
| Davidson County | 3 | $19.65 | 7 | $35.50 |
| Sullivan County | 3 | $45.69 | 5 | $46.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 24 to 175 | 9 | $45.00 |
| 200 to 615 | 9 | $30.00 |
| 749 to 1,400 | 9 | $40.50 |
| 1,472 to 17,001 | 10 | $23.95 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261064 | Sullivan County | 1,000 | $45.69 | $45.69 | 1 | Summers-Taylor, Inc. | TDOT |
| 26 JUN 2026 | CN262049 | Marion County | 45 | $32.10 | $48.35 | 2 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 17,001 | $10.90 | $10.73 | 4 | Civil Constructors, LLC | TDOT |
| 08 MAY 2026 | CN263043 | Davidson County | 120 | $50.00 | $45.00 | 2 | Stansell Electric Company, Inc. | TDOT |
| 08 MAY 2026 | CN262043 | Hamilton County | 1,400 | $48.00 | $51.60 | 2 | Wright Brothers Construction Company, Inc. | TDOT |
| 20 MAR 2026 | CN263026 | Davidson County | 750 | $19.65 | $19.65 | 2 | Vulcan Construction Materials, LLC | TDOT |
| 20 MAR 2026 | CN262024 | Hamilton County | 24 | $90.00 | $82.50 | 2 | APAC-Atlantic, Inc. | TDOT |
| 20 MAR 2026 | CN262026 | Hamilton County | 175 | $55.75 | $61.33 | 2 | Wright Brothers Construction Company, Inc. | TDOT |
| 06 FEB 2026 | CN261011 | Sevier County | 3,656 | $22.89 | $22.89 | 1 | Charles Blalock & Sons, Inc. | TDOT |
| 05 DEC 2025 | CNZ336 | Dyer County | 940 | $73.00 | $73.00 | 1 | Ford Construction Company | TDOT |
| 05 DEC 2025 | CNZ293 | Putnam County | 48 | $27.00 | $26.93 | 2 | Vulcan Construction Materials, LLC | TDOT |
| 05 DEC 2025 | CNZ276 | Sullivan County | 3,769 | $30.00 | $43.16 | 2 | Nicholas Overbay DBA East Tennessee Turf and Landscape | TDOT |
| 05 DEC 2025 | CNZ128 | Sullivan County | 363 | $70.30 | $58.40 | 2 | W-L Construction & Paving, Inc. | TDOT |
| 03 OCT 2025 | CNZ267 | Hamilton County | 207 | $28.00 | $29.70 | 2 | Dement Construction Group, LLC | TDOT |
| 03 OCT 2025 | CNZ266 | Trousdale County | 66 | $28.00 | $36.41 | 4 | Bell & Associates Construction, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way