Metal beam guard fence unit price, Tennessee
Low bidders on TDOT contracts carried a median of $97.25 per LF for item 705-01.04, metal beam guard fence, over the 24 months to 02 OCT 2026, across 24 low bids. Half of all 84 bids fell between $88.94 and $120.33.
- Owner
- Tennessee DOT
- Item
- 705-01.04
- Unit
- LF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 7 | 7 | $70.68 | 20 | $70.47 |
| 2020 | 2 | 2 | $75.39 | 11 | $78.00 |
| 2023 | 1 | 1 | $133.00 | 2 | $110.59 |
| 2024 | 12 | 12 | $100.00 | 33 | $107.00 |
| 2025 | 10 | 10 | $106.72 | 29 | $115.00 |
| 2026 | 10 | 10 | $80.00 | 41 | $95.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 6 to 50 | 6 | $108.28 |
| 50 to 88 | 6 | $83.32 |
| 88 to 125 | 6 | $101.00 |
| 125 to 394 | 6 | $93.75 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN263064 | Bedford County | 125 | $100.00 | $100.00 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 70 | $80.00 | $80.00 | 5 | Southern Constructors, Inc. | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 33 | $79.80 | $85.00 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 39 | $89.25 | $100.52 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 104 | $105.00 | $112.50 | 4 | Civil Constructors, LLC | TDOT |
| 20 MAR 2026 | CN261015 | Anderson County | 54 | $83.60 | $84.00 | 5 | Whaley Construction, LLC | TDOT |
| 20 MAR 2026 | CN261013 | Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington | 150 | $76.00 | $76.00 | 3 | Tennessee Guardrail, Inc. | TDOT |
| 20 MAR 2026 | CN263037 | Counties Bedford, Cheatham, Davidson, Dickson, Giles, Hickman, Houston, Humphreys, Lawrence, Lewis, Lincoln, Macon, Marshall, Maury, Montgomery, Moore, Perry, Robertson, Rutherford, Smith, Stewart, Sumner, Trousdale, Wayne, Williamson, And Wilson | 50 | $60.00 | $103.00 | 3 | Reynolds Fence and Guardrail, Inc. | TDOT |
| 20 MAR 2026 | CN264030 | Counties Benton, Carroll, Chester, Crockett, Decatur, Dyer, Fayette, Gibson, Hardeman, Hardin, Haywood, Henderson, Henry, Lake, Lauderdale, Madison, Mcnairy, Obion, Shelby, Tipton, And Weakley | 200 | $60.00 | $130.00 | 3 | Reynolds Fence and Guardrail, Inc. | TDOT |
| 20 MAR 2026 | CN262036 | Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And White | 100 | $80.00 | $85.00 | 4 | Reynolds Fence and Guardrail, Inc. | TDOT |
| 03 OCT 2025 | CNZ278 | Carter County | 125 | $110.00 | $98.50 | 2 | Southern Constructors, Inc. | TDOT |
| 03 OCT 2025 | CNZ252 | Cocke County | 88 | $97.00 | $100.76 | 3 | Adams Contracting, LLC | TDOT |
| 03 OCT 2025 | CNZ111 | Putnam County | 50 | $103.45 | $115.00 | 7 | Rogers Group, Inc. | TDOT |
| 15 AUG 2025 | CNZ215 | Benton County | 88 | $112.50 | $121.25 | 2 | Thomson & Thomson, Inc. | TDOT |
| 15 AUG 2025 | CNZ210 | Claiborne County | 6 | $125.00 | $125.00 | 1 | Southern Constructors, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.