TDOT contract CNZ081 bid tabulation
The construction of a 40' x 60' salt brine shed at i-24 (exit 24) in coopertown. Let by Tennessee DOT on March 21, 2025, Robertson County. 2 bids received; low bid $76,812 by H & H Construction, Inc..
- Owner
- Tennessee DOT
- Letting
- 21 MAR 2025
- Pay items
- 2
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | H & H Construction, Inc. | $76,812 | Low |
| 2 | Mountain Home Construction LLC | $78,001 | +2.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. H & H Construction, Inc. | 2. Mountain Home Construction LLC |
|---|---|---|---|---|---|
| 1 | Building (40' X 60') (680-02.01) | EACH | 1 | $72,971 | $78,000 |
| 2 | Mobilization (717-01) | LS | 1 | $3,840.60 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of March 21, 2025. Compiled by Mirage Metrics.