TDOT contract CNZ724 bid tabulation
The mowing on various state routes. Let by Tennessee DOT on November 7, 2025, Counties Macon, Smith, And Trousdale. 2 bids received; low bid $1,095,660 by Ace Clearing & Construction, Inc..
- Owner
- Tennessee DOT
- Letting
- 07 NOV 2025
- Pay items
- 3
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ace Clearing & Construction, Inc. | $1,095,660 | Low |
| 2 | Salazar Contracting, LLC | $1,314,792 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ace Clearing & Construction, Inc. | 2. Salazar Contracting, LLC |
|---|---|---|---|---|---|
| 1 | Mowing (year 1) (806-01.11) | ACRE | 4,058 | $86.00 | $120.00 |
| 2 | Mowing (year 2) (806-01.12) | ACRE | 4,058 | $90.00 | $108.00 |
| 3 | Mowing (year 3) (806-01.13) | ACRE | 4,058 | $94.00 | $96.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of November 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.