Machined rip-rap (class a-1) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $69.94 per TON for item 709-05.06, machined rip-rap (class a-1), over the 24 months to 02 OCT 2026, across 98 low bids. Half of all 339 bids fell between $60.00 and $90.38.
- Owner
- Tennessee DOT
- Item
- 709-05.06
- Unit
- TON
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 5 | 5 | $39.23 | 19 | $35.00 |
| 2019 | 1 | 1 | $65.00 | 4 | $82.50 |
| 2020 | 9 | 9 | $45.00 | 34 | $44.50 |
| 2023 | 7 | 7 | $65.00 | 21 | $73.00 |
| 2024 | 47 | 47 | $64.00 | 148 | $70.00 |
| 2025 | 40 | 40 | $75.25 | 142 | $74.75 |
| 2026 | 36 | 36 | $69.00 | 132 | $75.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Shelby County | 6 | $74.50 | 20 | $80.00 |
| Rutherford County | 4 | $86.38 | 18 | $68.72 |
| Cumberland County | 4 | $51.21 | 16 | $54.50 |
| Williamson County | 3 | $69.00 | 14 | $75.00 |
| Sullivan County | 5 | $100.00 | 13 | $100.00 |
| Anderson County | 3 | $53.60 | 12 | $81.00 |
| Hawkins County | 3 | $85.00 | 9 | $88.97 |
| Chester County | 3 | $50.00 | 8 | $54.50 |
| Humphreys County | 3 | $70.00 | 7 | $75.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 12 to 84 | 24 | $77.50 |
| 85 to 258 | 25 | $68.00 |
| 302 to 754 | 24 | $70.34 |
| 780 to 24,990 | 25 | $64.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261074 | Claiborne County | 808 | $78.00 | $80.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 320 | $50.00 | $60.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 304 | $100.00 | $100.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 123 | $105.00 | $105.00 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 130 | $180.07 | $180.07 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 46 | $64.00 | $65.00 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 207 | $56.00 | $56.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 14,469 | $50.63 | $52.31 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 1,315 | $95.00 | $91.00 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN262060 | Meigs County | 117 | $141.16 | $150.00 | 5 | Mid-State Construction Company, Inc. | TDOT |
| 14 AUG 2026 | CN264054 | Shelby County | 1,068 | $75.00 | $82.50 | 2 | Dement Construction Group, LLC | TDOT |
| 14 AUG 2026 | CN264052 | Tipton County | 114 | $68.00 | $68.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 14 AUG 2026 | CN263061 | Humphreys County | 50 | $125.00 | $125.00 | 1 | Dement Construction Group, LLC | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 91 | $50.00 | $52.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264903 | Dyer County | 197 | $61.00 | $65.50 | 2 | Ford Construction Company | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.