High-visibility construction fence unit price, Tennessee
Low bidders on TDOT contracts carried a median of $3.25 per LF for item 707-08.11, high-visibility construction fence, over the 24 months to 02 OCT 2026, across 100 low bids. Half of all 358 bids fell between $2.50 and $4.99.
- Owner
- Tennessee DOT
- Item
- 707-08.11
- Unit
- LF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 5 | 5 | $2.50 | 19 | $2.50 |
| 2019 | 1 | 1 | $2.00 | 4 | $2.70 |
| 2020 | 14 | 14 | $3.81 | 54 | $2.50 |
| 2023 | 5 | 5 | $6.50 | 15 | $6.50 |
| 2024 | 49 | 49 | $3.50 | 164 | $3.55 |
| 2025 | 40 | 40 | $3.33 | 144 | $3.42 |
| 2026 | 42 | 42 | $3.09 | 157 | $3.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Shelby County | 7 | $4.00 | 23 | $3.85 |
| Cumberland County | 4 | $3.42 | 19 | $3.30 |
| Coffee County | 4 | $3.15 | 17 | $2.55 |
| Sumner County | 3 | $1.82 | 16 | $2.02 |
| Carter County | 4 | $6.23 | 11 | $6.30 |
| Rutherford County | 3 | $2.20 | 10 | $2.50 |
| Humphreys County | 3 | $3.90 | 10 | $3.95 |
| Hawkins County | 3 | $7.00 | 9 | $6.00 |
| Dyer County | 3 | $2.50 | 6 | $2.75 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 43 to 400 | 25 | $6.10 |
| 400 to 885 | 25 | $4.00 |
| 900 to 2,138 | 25 | $3.00 |
| 2,300 to 496,855 | 25 | $2.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN263064 | Bedford County | 200 | $4.00 | $3.73 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN261070 | Carter County | 110 | $6.37 | $6.20 | 3 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261067 | Carter County | 300 | $10.75 | $6.33 | 4 | Eclipse Companies,LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 660 | $4.00 | $4.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261069 | Cocke County | 772 | $4.95 | $4.72 | 4 | Whaley Construction, LLC | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 1,290 | $2.50 | $2.50 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 600 | $6.00 | $6.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 436 | $5.60 | $5.60 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 700 | $3.18 | $3.18 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 259 | $5.00 | $3.56 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 1,910 | $3.39 | $3.39 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 960 | $2.85 | $2.84 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 2,894 | $2.50 | $2.55 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 24,110 | $1.84 | $2.27 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 520 | $2.75 | $2.75 | 1 | Ford Construction Company | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.