Guardrail removed unit price, Tennessee
Low bidders on TDOT contracts carried a median of $3.00 per LF for item 706-01, guardrail removed, over the 24 months to 02 OCT 2026, across 215 low bids. Half of all 589 bids fell between $1.05 and $4.75.
- Owner
- Tennessee DOT
- Item
- 706-01
- Unit
- LF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 40 | 40 | $1.14 | 101 | $1.17 |
| 2020 | 18 | 18 | $1.26 | 50 | $1.00 |
| 2023 | 11 | 11 | $5.25 | 24 | $3.67 |
| 2024 | 69 | 69 | $4.00 | 199 | $4.00 |
| 2025 | 97 | 97 | $3.50 | 256 | $3.00 |
| 2026 | 94 | 94 | $1.90 | 261 | $1.40 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 9 | $1.00 | 40 | $1.02 |
| Shelby County | 9 | $4.05 | 25 | $4.50 |
| Maury County | 6 | $3.08 | 25 | $1.15 |
| Sumner County | 6 | $1.06 | 20 | $1.02 |
| Knox County | 4 | $2.52 | 16 | $3.80 |
| Henderson County | 5 | $3.50 | 15 | $4.24 |
| Humphreys County | 4 | $3.00 | 15 | $2.00 |
| Roane County | 3 | $1.10 | 14 | $1.54 |
| Sullivan County | 7 | $3.73 | 14 | $2.75 |
| Gibson County | 6 | $3.88 | 13 | $4.00 |
| Benton County | 4 | $2.25 | 12 | $4.00 |
| Hamilton County | 5 | $1.15 | 12 | $1.17 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 10 to 150 | 53 | $2.10 |
| 150 to 325 | 54 | $2.00 |
| 330 to 756 | 54 | $4.00 |
| 775 to 20,295 | 54 | $2.90 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261065 | Campbell And Morgan Counties | 225 | $1.00 | $1.60 | 4 | Mountain Home Construction LLC | TDOT |
| 02 OCT 2026 | CN261070 | Carter County | 680 | $10.00 | $2.00 | 3 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261067 | Carter County | 150 | $1.50 | $2.65 | 4 | Eclipse Companies,LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 401 | $4.00 | $3.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261069 | Cocke County | 32 | $1.39 | $1.42 | 4 | Whaley Construction, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 898 | $2.00 | $1.40 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 50 | $1.20 | $1.20 | 3 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 923 | $1.00 | $1.16 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 64 | $3.18 | $3.18 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 2,276 | $1.00 | $2.17 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 590 | $3.80 | $3.80 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 210 | $4.75 | $4.75 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 840 | $2.00 | $1.02 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 217 | $6.65 | $6.65 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 276 | $1.50 | $1.25 | 5 | Mack Construction, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.