Thrie beam bridge transition mash tl-3 unit price, Tennessee
Low bidders on TDOT contracts carried a median of $3,100.00 per EACH for item 705-06.25, thrie beam bridge transition mash tl-3, over the 24 months to 02 OCT 2026, across 45 low bids. Half of all 151 bids fell between $2,642.50 and $3,535.00.
- Owner
- Tennessee DOT
- Item
- 705-06.25
- Unit
- EACH
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 6 | 6 | $2,003.69 | 17 | $1,815.00 |
| 2023 | 4 | 4 | $3,150.00 | 11 | $3,000.00 |
| 2024 | 22 | 22 | $2,975.00 | 65 | $2,978.00 |
| 2025 | 19 | 19 | $3,100.00 | 63 | $3,000.00 |
| 2026 | 20 | 20 | $3,091.50 | 71 | $3,083.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Cumberland County | 3 | $3,161.60 | 14 | $3,190.80 |
| Hawkins County | 3 | $3,570.00 | 9 | $3,570.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 11 | $2,970.00 |
| 2 to 4 | 11 | $3,300.00 |
| 4 to 6 | 11 | $3,225.00 |
| 6 to 14 | 12 | $3,030.80 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261074 | Claiborne County | 1 | $3,350.00 | $3,350.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 4 | $2,500.00 | $2,500.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 8 | $3,931.31 | $3,931.31 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 8 | $2,900.00 | $3,061.22 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 8 | $3,161.60 | $3,280.80 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN262060 | Meigs County | 3 | $3,458.40 | $3,458.40 | 5 | Mid-State Construction Company, Inc. | TDOT |
| 14 AUG 2026 | CN264054 | Shelby County | 8 | $2,800.00 | $2,900.00 | 2 | Dement Construction Group, LLC | TDOT |
| 26 JUN 2026 | CN264049 | Dyer County | 7 | $2,650.00 | $2,650.00 | 3 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 8 | $3,570.00 | $3,905.86 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 4 | $3,380.00 | $3,177.50 | 4 | Civil Constructors, LLC | TDOT |
| 26 JUN 2026 | CN263055 | Williamson County | 1 | $3,083.00 | $2,947.37 | 5 | Bell & Associates Construction, LLC | TDOT |
| 08 MAY 2026 | CN261051 | Anderson County | 2 | $3,850.00 | $2,710.00 | 4 | J. Hill Excavating, LLC | TDOT |
| 08 MAY 2026 | CN264039 | Henderson County | 2 | $2,500.00 | $2,500.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 08 MAY 2026 | CN264036 | Henry County | 4 | $2,500.00 | $2,650.00 | 4 | Delta Contracting Company, LLC | TDOT |
| 20 MAR 2026 | CN261013 | Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington | 2 | $2,300.00 | $2,300.00 | 3 | Tennessee Guardrail, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.