Gr terminal (energy absorbing) mash tl-2 unit price, Tennessee
Low bidders on TDOT contracts carried a median of $3,400.00 per EACH for item 705-06.30, gr terminal (energy absorbing) mash tl-2, over the 24 months to 02 OCT 2026, across 102 low bids. Half of all 293 bids fell between $3,100.00 and $3,675.00.
- Owner
- Tennessee DOT
- Item
- 705-06.30
- Unit
- EACH
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2023 | 4 | 4 | $3,614.00 | 8 | $3,550.00 |
| 2024 | 48 | 48 | $3,630.00 | 130 | $3,555.26 |
| 2025 | 45 | 45 | $3,465.00 | 110 | $3,465.00 |
| 2026 | 42 | 42 | $3,225.00 | 141 | $3,260.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Sumner County | 5 | $3,450.00 | 17 | $3,450.00 |
| Hawkins County | 5 | $3,500.00 | 14 | $3,465.40 |
| Monroe County | 3 | $3,375.00 | 11 | $2,900.00 |
| Anderson County | 3 | $3,117.00 | 11 | $3,000.00 |
| Sullivan County | 4 | $3,385.00 | 8 | $3,470.56 |
| Hamilton County | 3 | $3,565.00 | 6 | $3,482.50 |
| Johnson County | 3 | $3,500.00 | 4 | $3,500.87 |
| Unicoi County | 3 | $3,750.00 | 3 | $3,750.00 |
| Washington County | 3 | $3,800.00 | 3 | $3,800.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 25 | $3,468.00 |
| 2 to 3 | 26 | $3,349.00 |
| 3 to 6 | 25 | $3,400.00 |
| 6 to 55 | 26 | $3,300.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN263064 | Bedford County | 4 | $3,025.00 | $2,987.50 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN261065 | Campbell And Morgan Counties | 5 | $3,000.00 | $3,062.50 | 4 | Mountain Home Construction LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 1 | $3,200.00 | $3,100.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 8 | $3,300.00 | $3,300.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 6 | $3,000.00 | $3,000.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 3 | $3,200.00 | $3,368.00 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 1 | $3,501.74 | $3,501.74 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 3 | $4,000.00 | $3,770.00 | 4 | Rock Supremacy, LLC | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 1 | $2,971.50 | $3,175.00 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN263048 | Bedford County | 2 | $3,250.00 | $3,020.62 | 4 | Hawkins Asphalt Paving, LLC | TDOT |
| 26 JUN 2026 | CN264049 | Dyer County | 1 | $3,000.00 | $3,000.00 | 3 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN261055 | Hawkins County | 6 | $3,600.00 | $3,650.00 | 2 | Summers-Taylor, Inc. | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 2 | $2,887.50 | $3,227.40 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN261901 | Johnson County | 3 | $3,200.00 | $3,979.92 | 2 | Southern Constructors, Inc. | TDOT |
| 26 JUN 2026 | CN263050 | Macon County | 1 | $3,412.33 | $3,200.00 | 4 | Rogers Group, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.