Machined rip-rap (class a-3) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $68.23 per TON for item 709-05.05, machined rip-rap (class a-3), over the 24 months to 02 OCT 2026, across 113 low bids. Half of all 390 bids fell between $57.53 and $88.57.
- Owner
- Tennessee DOT
- Item
- 709-05.05
- Unit
- TON
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 9 | 9 | $46.00 | 36 | $47.00 |
| 2019 | 1 | 1 | $65.00 | 4 | $82.50 |
| 2020 | 13 | 13 | $45.00 | 47 | $45.00 |
| 2023 | 4 | 4 | $65.38 | 14 | $66.88 |
| 2024 | 50 | 50 | $65.00 | 165 | $68.84 |
| 2025 | 44 | 44 | $70.88 | 147 | $69.75 |
| 2026 | 43 | 43 | $67.00 | 163 | $72.38 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 5 | $60.25 | 20 | $60.62 |
| Shelby County | 5 | $75.85 | 17 | $80.00 |
| Anderson County | 4 | $64.12 | 16 | $85.00 |
| Cumberland County | 4 | $53.49 | 16 | $60.81 |
| Williamson County | 3 | $50.00 | 14 | $71.00 |
| Coffee County | 3 | $55.00 | 13 | $56.00 |
| Humphreys County | 3 | $80.00 | 12 | $77.50 |
| Campbell County | 3 | $55.65 | 10 | $60.33 |
| Sullivan County | 4 | $88.84 | 10 | $95.88 |
| Hamilton County | 3 | $100.00 | 9 | $100.00 |
| Carter County | 3 | $89.98 | 9 | $113.00 |
| Chester County | 3 | $50.00 | 8 | $54.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 10 to 100 | 28 | $80.00 |
| 100 to 150 | 28 | $79.50 |
| 152 to 300 | 28 | $59.28 |
| 312 to 8,180 | 29 | $60.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261076 | Anderson County | 89 | $60.00 | $89.00 | 4 | Rogers Group, Inc. | TDOT |
| 02 OCT 2026 | CN263064 | Bedford County | 200 | $50.00 | $55.00 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN261070 | Carter County | 282 | $89.98 | $89.98 | 3 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261067 | Carter County | 100 | $182.75 | $153.88 | 4 | Eclipse Companies,LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 100 | $95.00 | $87.62 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261069 | Cocke County | 213 | $85.21 | $72.51 | 4 | Whaley Construction, LLC | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 270 | $50.00 | $60.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 50 | $100.00 | $100.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 100 | $80.00 | $73.69 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 250 | $105.00 | $105.00 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 100 | $80.00 | $82.50 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 101 | $87.69 | $87.69 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 100 | $55.65 | $55.65 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 200 | $56.00 | $56.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 727 | $49.35 | $52.17 | 6 | Charles Blalock & Sons, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.