Plastic pavement marking (wrong way arrow) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $322.89 per EACH for item 716-04.06, plastic pavement marking (wrong way arrow), over the 24 months to 02 OCT 2026, across 42 low bids. Half of all 118 bids fell between $251.25 and $420.75.
- Owner
- Tennessee DOT
- Item
- 716-04.06
- Unit
- EACH
- Latest letting
- 14 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 5 | 5 | $150.00 | 10 | $150.00 |
| 2023 | 7 | 7 | $350.00 | 16 | $332.50 |
| 2024 | 13 | 12 | $312.50 | 31 | $360.00 |
| 2025 | 26 | 26 | $340.00 | 70 | $350.00 |
| 2026 | 9 | 9 | $265.00 | 28 | $331.25 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Maury County | 3 | $368.00 | 12 | $417.50 |
| Davidson County | 3 | $350.00 | 10 | $350.00 |
| Shelby County | 3 | $476.34 | 8 | $474.41 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 10 | $325.00 |
| 1 to 2 | 11 | $315.79 |
| 2 to 4 | 10 | $329.18 |
| 4 to 36 | 11 | $330.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 14 AUG 2026 | CN262056 | Grundy County | 4 | $265.00 | $265.00 | 5 | Mack Construction, LLC | TDOT |
| 26 JUN 2026 | CN263052 | Maury County | 1 | $1,200.00 | $421.05 | 7 | Eubank Asphalt Paving & Sealing, LLC | TDOT |
| 20 MAR 2026 | CN261027 | Unicoi County | 4 | $265.00 | $265.00 | 1 | Summers-Taylor, Inc. | TDOT |
| 20 MAR 2026 | CN263036 | Williamson County | 1 | $350.00 | $350.00 | 3 | Vulcan Construction Materials, LLC | TDOT |
| 20 MAR 2026 | CN263025 | Davidson County | 1 | $350.00 | $350.00 | 3 | Vulcan Construction Materials, LLC | TDOT |
| 06 FEB 2026 | CN261007 | Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington | 1 | $137.98 | $225.00 | 3 | Mullen's Markings, Inc | TDOT |
| 06 FEB 2026 | CN263004 | Counties Bedford, Cheatham, Davidson, Dickson, Giles, Hickman, Houston, Humphreys, Lawrence, Lewis, Lincoln, Macon, Marshall, Maury, Montgomery, Moore, Perry, Robertson, Rutherford, Smith, Stewart, Sumner, Trousdale, Wayne, Williamson, And Wilson | 3 | $250.00 | $250.00 | 2 | Reynolds Sealing & Striping, Inc. | TDOT |
| 06 FEB 2026 | CN264001 | Counties Benton, Carroll, Chester, Crockett, Decatur, Dyer, Fayette, Gibson, Hardeman, Hardin, Haywood, Henderson, Henry, Lake, Lauderdale, Madison, Mcnairy, Obion, Shelby, Tipton, And Weakley | 1 | $450.00 | $450.00 | 1 | Traf-Mark Industries, L.L.C. | TDOT |
| 06 FEB 2026 | CN262003 | Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And White | 2 | $142.41 | $250.00 | 3 | Mullen's Markings, Inc | TDOT |
| 05 DEC 2025 | CNZ333 | Carroll County | 4 | $450.00 | $450.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 05 DEC 2025 | CNZ327 | Cumberland County | 4 | $290.35 | $320.18 | 2 | Rogers Group, Inc. | TDOT |
| 05 DEC 2025 | CNZ298 | Knox County | 4 | $400.00 | $385.00 | 3 | APAC-Atlantic, Inc. | TDOT |
| 05 DEC 2025 | CNZ292 | Marion County | 6 | $425.00 | $362.50 | 2 | Rogers Group, Inc. | TDOT |
| 05 DEC 2025 | CNZ335 | Maury County | 4 | $300.00 | $350.00 | 3 | Volunteer Paving, LLC | TDOT |
| 05 DEC 2025 | CNZ328 | Mcminn County | 2 | $260.00 | $257.50 | 2 | Wright Brothers Construction Company, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.