Painted pavement marking (4" line) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $1,200.00 per LM for item 716-05.01, painted pavement marking (4" line), over the 24 months to 02 OCT 2026, across 143 low bids. Half of all 385 bids fell between $990.00 and $2,600.00.
- Owner
- Tennessee DOT
- Item
- 716-05.01
- Unit
- LM
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 75 | 75 | $765.00 | 159 | $845.00 |
| 2020 | 10 | 9 | $1,500.00 | 31 | $1,500.00 |
| 2023 | 1 | 1 | $2,510.00 | 2 | $3,180.00 |
| 2024 | 67 | 67 | $1,400.00 | 171 | $1,500.00 |
| 2025 | 62 | 62 | $1,100.00 | 160 | $1,276.01 |
| 2026 | 59 | 59 | $1,110.00 | 164 | $1,262.50 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 5 | $1,001.24 | 24 | $1,032.50 |
| Hamilton County | 10 | $1,308.00 | 20 | $1,298.00 |
| Cannon County | 3 | $945.00 | 14 | $1,000.00 |
| Cumberland County | 6 | $839.50 | 14 | $854.75 |
| Coffee County | 3 | $1,000.00 | 8 | $1,487.50 |
| Marion County | 4 | $1,046.06 | 8 | $1,153.68 |
| Polk County | 5 | $1,600.00 | 8 | $1,662.50 |
| Overton County | 3 | $976.75 | 7 | $950.00 |
| White County | 3 | $997.50 | 7 | $997.50 |
| Bradley County | 3 | $1,157.89 | 6 | $1,191.45 |
| Fentress County | 3 | $924.00 | 5 | $924.00 |
| Mcminn County | 4 | $900.00 | 4 | $900.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LM) | Low bids | Low-bid median |
|---|---|---|
| 0.01 to 1.01 | 35 | $3,500.00 |
| 1.38 to 12.40 | 36 | $1,105.00 |
| 13 to 24.10 | 36 | $1,044.75 |
| 24.40 to 300 | 36 | $975.88 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261076 | Anderson County | 0.20 | $3,015.00 | $3,325.00 | 4 | Rogers Group, Inc. | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 0.56 | $2,200.00 | $2,200.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 1 | $3,500.00 | $3,780.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 0.40 | $2,000.00 | $2,105.00 | 6 | Dement Construction Group, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 16.03 | $918.75 | $944.38 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 2.40 | $3,200.00 | $3,200.00 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN263060 | Counties Lawrence, Lewis, Perry, And Wayne | 157 | $800.00 | $1,200.00 | 3 | Superior Traffic Control, LLC | TDOT |
| 26 JUN 2026 | CN262047 | Fentress County | 27.30 | $839.45 | $817.23 | 2 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN262054 | Franklin County | 24.10 | $1,177.00 | $1,177.00 | 1 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN262048 | Grundy County | 45.10 | $1,075.00 | $1,075.00 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 1 | $1,650.00 | $1,604.73 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN263045 | Counties Hickman, Lincoln, And Marshall | 151.20 | $800.00 | $800.00 | 3 | Superior Traffic Control, LLC | TDOT |
| 26 JUN 2026 | CN264037 | Lake County | 2.85 | $2,950.00 | $2,950.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN262049 | Marion County | 18.36 | $850.65 | $890.33 | 2 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN263052 | Maury County | 1.01 | $2,500.00 | $2,083.50 | 8 | Eubank Asphalt Paving & Sealing, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way