Painted pavement marking (6" line) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $1,425.00 per LM for item 716-05.20, painted pavement marking (6" line), over the 24 months to 02 OCT 2026, across 331 low bids. Half of all 871 bids fell between $1,200.00 and $2,200.00.
- Owner
- Tennessee DOT
- Item
- 716-05.20
- Unit
- LM
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 13 | 13 | $1,470.00 | 25 | $1,500.00 |
| 2020 | 41 | 41 | $900.00 | 89 | $909.00 |
| 2022 | 2 | 2 | $2,800.00 | 4 | $2,570.00 |
| 2023 | 16 | 16 | $1,400.00 | 35 | $1,375.00 |
| 2024 | 104 | 104 | $1,400.00 | 290 | $1,400.00 |
| 2025 | 161 | 161 | $1,475.00 | 414 | $1,460.00 |
| 2026 | 128 | 128 | $1,400.00 | 334 | $1,500.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Davidson County | 18 | $1,275.00 | 57 | $1,350.00 |
| Knox County | 12 | $995.00 | 40 | $1,075.00 |
| Williamson County | 9 | $1,300.00 | 40 | $1,400.00 |
| Shelby County | 13 | $3,391.53 | 36 | $3,372.39 |
| Rutherford County | 8 | $1,300.00 | 32 | $1,500.00 |
| Maury County | 8 | $1,350.00 | 32 | $1,522.50 |
| Anderson County | 6 | $1,020.00 | 21 | $1,312.50 |
| Sumner County | 6 | $1,500.00 | 18 | $1,294.57 |
| Hawkins County | 7 | $1,300.00 | 17 | $1,300.00 |
| Henderson County | 6 | $1,325.00 | 17 | $1,200.00 |
| Monroe County | 5 | $1,312.50 | 17 | $1,312.50 |
| Bedford County | 4 | $1,282.50 | 16 | $1,382.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LM) | Low bids | Low-bid median |
|---|---|---|
| 0.03 to 8 | 82 | $2,317.86 |
| 8 to 19.35 | 83 | $1,250.00 |
| 19.50 to 34.70 | 83 | $1,300.00 |
| 34.80 to 200 | 83 | $1,500.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261070 | Carter County | 0.20 | $9,422.90 | $3,094.15 | 3 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 0.80 | $3,500.00 | $3,780.00 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 1 | $2,500.00 | $2,500.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 34 | $1,800.00 | $1,800.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 0.60 | $3,183.40 | $3,183.40 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 3 | $2,215.71 | $2,215.71 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 1 | $2,585.00 | $2,585.00 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 2.10 | $3,200.00 | $3,200.00 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 0.70 | $1,312.50 | $1,437.50 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN263048 | Bedford County | 2.60 | $1,000.00 | $1,187.50 | 4 | Hawkins Asphalt Paving, LLC | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 1.66 | $3,900.00 | $3,900.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263059 | Dickson And Hickman Counties | 3.60 | $2,500.00 | $2,500.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 26 JUN 2026 | CN264043 | Dyer County | 48 | $2,695.00 | $2,695.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN264903 | Dyer County | 2 | $3,000.00 | $3,100.00 | 2 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN261054 | Greene County | 19 | $1,250.00 | $1,250.00 | 1 | Summers-Taylor, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.