Removal of pavement marking (channelization striping) unit price, Tennessee

Low bidders on TDOT contracts carried a median of $16.95 per SY for item 716-08.04, removal of pavement marking (channelization striping), over the 24 months to 02 OCT 2026, across 40 low bids. Half of all 132 bids fell between $11.44 and $25.16.

Owner
Tennessee DOT
Item
716-08.04
Unit
SY
Latest letting
02 OCT 2026
$16.95Low bidder's median, per SY
$15.38Median of all bids, per SY
41Contracts in the window

By year of letting

Removal of pavement marking (channelization striping), TDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201888$13.5018$13.50
202011$9.605$18.75
20241313$15.3842$15.20
20251918$19.0057$20.00
20261616$13.8049$15.00
Removal of pavement marking (channelization striping), TDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Removal of pavement marking (channelization striping), TDOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
Williamson County4$23.2019$20.00
Rutherford County4$11.3018$11.73
Removal of pavement marking (channelization striping), TDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Removal of pavement marking (channelization striping), TDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
6 to 2510$17.50
30 to 10010$25.00
114 to 40010$12.71
438 to 1,99710$19.00
Removal of pavement marking (channelization striping), TDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TDOT contracts carrying Removal of pavement marking (channelization striping)
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
02 OCT 2026CN264061Henry And Stewart Counties190$20.00$20.003Delta Contracting Company, LLCTDOT
26 JUN 2026CN263051Marshall And Williamson Counties40$31.50$30.754Asphalt Paving Systems, Inc.TDOT
26 JUN 2026CN264051Mcnairy County6$52.50$52.502Asphalt Paving Systems, Inc.TDOT
26 JUN 2026CN263057Rutherford County100$8.60$8.384Civil Constructors, LLCTDOT
26 JUN 2026CN263054Williamson County36$20.00$20.004Volunteer Paving, LLCTDOT
26 JUN 2026CN263055Williamson County88$30.00$28.005Bell & Associates Construction, LLCTDOT
20 MAR 2026CN263027Davidson County525$8.00$20.003Vulcan Construction Materials, LLCTDOT
20 MAR 2026CN262023Grundy And Sequatchie Counties30$12.36$12.682Asphalt Paving Systems, Inc.TDOT
06 FEB 2026CN261007Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington12$10.00$14.003Mullen's Markings, IncTDOT
06 FEB 2026CN263004Counties Bedford, Cheatham, Davidson, Dickson, Giles, Hickman, Houston, Humphreys, Lawrence, Lewis, Lincoln, Macon, Marshall, Maury, Montgomery, Moore, Perry, Robertson, Rutherford, Smith, Stewart, Sumner, Trousdale, Wayne, Williamson, And Wilson10$15.00$15.002Reynolds Sealing & Striping, Inc.TDOT
06 FEB 2026CN264001Counties Benton, Carroll, Chester, Crockett, Decatur, Dyer, Fayette, Gibson, Hardeman, Hardin, Haywood, Henderson, Henry, Lake, Lauderdale, Madison, Mcnairy, Obion, Shelby, Tipton, And Weakley50$40.00$40.001Traf-Mark Industries, L.L.C.TDOT
06 FEB 2026CN262003Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And White350$11.00$12.003Mullen's Markings, IncTDOT
06 FEB 2026CN262005Clay And Overton Counties1,997$10.50$10.313Asphalt Paving Systems, Inc.TDOT
06 FEB 2026CN264008Gibson County15$45.00$45.001Pavement Restorations, Inc.TDOT
06 FEB 2026CN263020Rutherford County8$12.60$15.006Asphalt Paving Systems, Inc.TDOT
Latest TDOT contracts carrying Removal of pavement marking (channelization striping)

Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.

How these prices were read

TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy