Removal of pavement marking (turn lane arrow) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $102.50 per EACH for item 716-08.06, removal of pavement marking (turn lane arrow), over the 24 months to 02 OCT 2026, across 45 low bids. Half of all 134 bids fell between $75.00 and $109.75.
- Owner
- Tennessee DOT
- Item
- 716-08.06
- Unit
- EACH
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 9 | 9 | $50.00 | 25 | $29.75 |
| 2020 | 1 | 1 | $105.00 | 2 | $104.50 |
| 2023 | 1 | 1 | $210.00 | 3 | $208.87 |
| 2024 | 15 | 15 | $100.00 | 38 | $92.50 |
| 2025 | 23 | 22 | $105.13 | 68 | $100.15 |
| 2026 | 17 | 17 | $89.25 | 48 | $83.20 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 4 | $75.00 | 16 | $80.15 |
| Williamson County | 3 | $75.00 | 15 | $100.00 |
| Gibson County | 3 | $200.00 | 6 | $204.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 11 | $100.00 |
| 2 to 5 | 11 | $105.26 |
| 5 to 13 | 11 | $102.50 |
| 15 to 62 | 12 | $86.62 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261075 | Counties Cocke, Hawkins, Jefferson, Monroe, Scott, And Washington | 1 | $100.00 | $100.00 | 3 | Stansell Electric Company, Inc. | TDOT |
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 12 | $150.00 | $150.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264051 | Mcnairy County | 6 | $220.50 | $220.50 | 2 | Asphalt Paving Systems, Inc. | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 56 | $57.30 | $55.77 | 4 | Civil Constructors, LLC | TDOT |
| 26 JUN 2026 | CN263054 | Williamson County | 12 | $75.00 | $51.25 | 4 | Volunteer Paving, LLC | TDOT |
| 26 JUN 2026 | CN263055 | Williamson County | 4 | $110.00 | $100.00 | 5 | Bell & Associates Construction, LLC | TDOT |
| 20 MAR 2026 | CN263027 | Davidson County | 3 | $125.00 | $100.00 | 3 | Vulcan Construction Materials, LLC | TDOT |
| 06 FEB 2026 | CN261007 | Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington | 2 | $50.00 | $50.00 | 3 | Mullen's Markings, Inc | TDOT |
| 06 FEB 2026 | CN263004 | Counties Bedford, Cheatham, Davidson, Dickson, Giles, Hickman, Houston, Humphreys, Lawrence, Lewis, Lincoln, Macon, Marshall, Maury, Montgomery, Moore, Perry, Robertson, Rutherford, Smith, Stewart, Sumner, Trousdale, Wayne, Williamson, And Wilson | 1 | $50.00 | $67.50 | 2 | Reynolds Sealing & Striping, Inc. | TDOT |
| 06 FEB 2026 | CN264001 | Counties Benton, Carroll, Chester, Crockett, Decatur, Dyer, Fayette, Gibson, Hardeman, Hardin, Haywood, Henderson, Henry, Lake, Lauderdale, Madison, Mcnairy, Obion, Shelby, Tipton, And Weakley | 1 | $250.00 | $250.00 | 1 | Traf-Mark Industries, L.L.C. | TDOT |
| 06 FEB 2026 | CN262003 | Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And White | 62 | $65.00 | $65.00 | 3 | Mullen's Markings, Inc | TDOT |
| 06 FEB 2026 | CN262004 | Cannon County | 1 | $76.50 | $76.91 | 2 | Asphalt Paving Systems, Inc. | TDOT |
| 06 FEB 2026 | CN262005 | Clay And Overton Counties | 9 | $78.75 | $78.75 | 3 | Asphalt Paving Systems, Inc. | TDOT |
| 06 FEB 2026 | CN264008 | Gibson County | 1 | $300.00 | $300.00 | 1 | Pavement Restorations, Inc. | TDOT |
| 06 FEB 2026 | CN262010 | Overton County | 2 | $105.00 | $103.09 | 3 | Asphalt Paving Systems, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.