Removal of pavement marking (stop line) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $10.00 per LF for item 716-08.05, removal of pavement marking (stop line), over the 24 months to 02 OCT 2026, across 53 low bids. Half of all 167 bids fell between $5.57 and $12.00.
- Owner
- Tennessee DOT
- Item
- 716-08.05
- Unit
- LF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 13 | 13 | $5.00 | 27 | $4.25 |
| 2020 | 1 | 1 | $14.50 | 2 | $13.50 |
| 2024 | 18 | 18 | $10.00 | 51 | $10.01 |
| 2025 | 25 | 24 | $8.02 | 78 | $10.00 |
| 2026 | 21 | 21 | $7.35 | 63 | $7.35 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 5 | $8.00 | 22 | $8.95 |
| Williamson County | 3 | $10.00 | 15 | $10.00 |
| Shelby County | 4 | $23.29 | 10 | $23.10 |
| Gibson County | 3 | $15.00 | 5 | $16.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 1 to 48 | 13 | $7.00 |
| 48 to 87 | 13 | $10.60 |
| 92 to 164 | 13 | $10.01 |
| 178 to 1,635 | 14 | $7.43 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261075 | Counties Cocke, Hawkins, Jefferson, Monroe, Scott, And Washington | 75 | $8.00 | $10.00 | 3 | Stansell Electric Company, Inc. | TDOT |
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 75 | $15.00 | $15.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 40 | $3.15 | $3.25 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN262048 | Grundy County | 78 | $6.50 | $6.50 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN263051 | Marshall And Williamson Counties | 501 | $10.50 | $10.53 | 4 | Asphalt Paving Systems, Inc. | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 1,233 | $5.75 | $5.57 | 4 | Civil Constructors, LLC | TDOT |
| 26 JUN 2026 | CN263054 | Williamson County | 52 | $10.00 | $5.12 | 4 | Volunteer Paving, LLC | TDOT |
| 26 JUN 2026 | CN263055 | Williamson County | 52 | $11.00 | $10.53 | 5 | Bell & Associates Construction, LLC | TDOT |
| 20 MAR 2026 | CN263027 | Davidson County | 25 | $12.00 | $8.00 | 3 | Vulcan Construction Materials, LLC | TDOT |
| 20 MAR 2026 | CN264019 | Hardeman County | 48 | $30.90 | $31.95 | 2 | Asphalt Paving Systems, Inc. | TDOT |
| 06 FEB 2026 | CN261007 | Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Greene, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington | 62 | $2.50 | $2.50 | 3 | Mullen's Markings, Inc | TDOT |
| 06 FEB 2026 | CN263004 | Counties Bedford, Cheatham, Davidson, Dickson, Giles, Hickman, Houston, Humphreys, Lawrence, Lewis, Lincoln, Macon, Marshall, Maury, Montgomery, Moore, Perry, Robertson, Rutherford, Smith, Stewart, Sumner, Trousdale, Wayne, Williamson, And Wilson | 20 | $7.00 | $7.00 | 2 | Reynolds Sealing & Striping, Inc. | TDOT |
| 06 FEB 2026 | CN264001 | Counties Benton, Carroll, Chester, Crockett, Decatur, Dyer, Fayette, Gibson, Hardeman, Hardin, Haywood, Henderson, Henry, Lake, Lauderdale, Madison, Mcnairy, Obion, Shelby, Tipton, And Weakley | 1 | $50.00 | $50.00 | 1 | Traf-Mark Industries, L.L.C. | TDOT |
| 06 FEB 2026 | CN262003 | Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And White | 1,635 | $3.00 | $3.00 | 3 | Mullen's Markings, Inc | TDOT |
| 06 FEB 2026 | CN262004 | Cannon County | 45 | $4.08 | $4.10 | 2 | Asphalt Paving Systems, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.