Plastic pavement marking (yield line) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $30.00 per SF for item 716-04.12, plastic pavement marking (yield line), over the 24 months to 02 OCT 2026, across 134 low bids. Half of all 342 bids fell between $18.00 and $40.00.
- Owner
- Tennessee DOT
- Item
- 716-04.12
- Unit
- SF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 20 | 20 | $13.20 | 41 | $13.32 |
| 2020 | 11 | 11 | $17.50 | 25 | $15.65 |
| 2023 | 7 | 7 | $30.10 | 12 | $30.05 |
| 2024 | 59 | 59 | $30.00 | 134 | $30.02 |
| 2025 | 72 | 72 | $30.00 | 196 | $30.30 |
| 2026 | 45 | 45 | $27.50 | 108 | $30.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Davidson County | 11 | $30.00 | 34 | $40.00 |
| Rutherford County | 5 | $31.58 | 22 | $35.02 |
| Sumner County | 5 | $41.75 | 15 | $33.00 |
| Hamilton County | 7 | $18.00 | 14 | $18.00 |
| Maury County | 4 | $33.38 | 12 | $33.38 |
| Coffee County | 3 | $37.00 | 9 | $20.20 |
| Sullivan County | 4 | $22.84 | 9 | $21.00 |
| Polk County | 3 | $16.80 | 8 | $22.00 |
| Shelby County | 3 | $40.22 | 8 | $38.91 |
| Marion County | 4 | $18.52 | 7 | $18.05 |
| Hawkins County | 3 | $22.00 | 6 | $18.57 |
| Mcminn County | 4 | $16.45 | 5 | $16.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 2 to 21 | 33 | $25.00 |
| 24 to 45 | 34 | $30.00 |
| 48 to 108 | 33 | $30.00 |
| 108 to 1,110 | 34 | $23.27 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261064 | Sullivan County | 80 | $24.69 | $24.69 | 1 | Summers-Taylor, Inc. | TDOT |
| 26 JUN 2026 | CN263048 | Bedford County | 27 | $30.00 | $30.00 | 4 | Hawkins Asphalt Paving, LLC | TDOT |
| 26 JUN 2026 | CN262047 | Fentress County | 108 | $15.85 | $15.43 | 2 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN262054 | Franklin County | 84 | $32.10 | $32.10 | 1 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN261054 | Greene County | 96 | $16.50 | $16.50 | 1 | Summers-Taylor, Inc. | TDOT |
| 26 JUN 2026 | CN264045 | Haywood County | 60 | $30.00 | $34.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN263045 | Counties Hickman, Lincoln, And Marshall | 9 | $40.00 | $40.00 | 3 | Superior Traffic Control, LLC | TDOT |
| 26 JUN 2026 | CN264037 | Lake County | 63 | $38.00 | $38.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN262049 | Marion County | 40 | $16.05 | $17.02 | 2 | Tinsley Asphalt, LLC | TDOT |
| 26 JUN 2026 | CN262050 | Mcminn County | 12 | $15.85 | $15.85 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN261049 | Sullivan County | 15 | $21.00 | $21.50 | 2 | Summers-Taylor, Inc. | TDOT |
| 26 JUN 2026 | CN264042 | Tipton County | 57 | $38.00 | $38.00 | 3 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN263054 | Williamson County | 45 | $30.00 | $35.00 | 4 | Volunteer Paving, LLC | TDOT |
| 08 MAY 2026 | CN261031 | Blount County | 120 | $16.00 | $16.00 | 3 | APAC-Atlantic, Inc. | TDOT |
| 08 MAY 2026 | CN261053 | Campbell County | 10 | $15.00 | $15.00 | 3 | Mountain Home Construction LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.