TxDOT contract A00212747 bid tabulation

TRAFFIC CONTROL SERVICES, US0290 (Various Locations in West Harris County to Various Locations in West Harris County). Let by Texas DOT on November 12, 2025, Harris, Houston District. 6 bids received; low bid $634,000 by Ross Sa Enterprise LLC, -18% against the engineer's estimate of $775,125.

Owner
Texas DOT
Letting
12 NOV 2025
Pay items
35
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ross Sa Enterprise LLC$634,000Low-18%
2Blue Chip Services, LLC$974,675+54%+26%
3Professional Traffic Control LLC$1,130,000+78%+46%
4Superior Traffic Control, LLC$1,567,145+147%+102%
5Awp Safety$1,712,540+170%+121%
6Republic Traffic Safety, Inc.$1,821,440+187%+135%
TxDOT contract A00212747: bids by rank

Engineer's estimate: $775,125.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Ross Sa Enterprise LLC2. Blue Chip Services, LLC3. Professional Traffic Control LLC4. Superior Traffic Control, LLC5. Awp Safety6. Republic Traffic Safety, Inc.
1Mobilization (callout) (500-7002)EACH65$500.00$1,000.00$500.00$1,000.00$100.00$1.00$1.00
2Mobilization (emergency) (500-7033)EACH5$300.00$1,500.00$400.00$500.00$500.00$1,000.00$750.00
3Portable changeable message sign (503-7001)DAY50$100.00$120.00$125.00$50.00$60.00$100.00$75.00
4TMA (stationary) (505-7001)DAY140$300.00$980.00$300.00$240.00$190.00$500.00$350.00
5TMA (mobile operation) (505-7003)DAY2,345$250.00$160.00$350.00$350.00$600.00$625.00$680.00
6Lane closure(setup & rem)(typ 1) (790-7001)EACH3$250.00$500.00$100.00$700.00$415.00$275.00$300.00
7Lane closure(setup & rem)(typ 2) (790-7002)EACH3$250.00$500.00$100.00$700.00$400.00$275.00$300.00
8Lane closure(setup & rem)(typ 5) (790-7005)EACH3$250.00$500.00$100.00$400.00$385.00$275.00$300.00
9Lane closure(setup & rem)(typ 6) (790-7006)EACH8$200.00$500.00$100.00$1,000.00$680.00$350.00$1,750.00
10Lane closure(setup & rem)(typ 7) (790-7007)EACH20$300.00$100.00$100.00$700.00$440.00$600.00$750.00
11Lane closure(setup & rem)(typ 8) (790-7008)EACH8$200.00$100.00$100.00$700.00$675.00$600.00$950.00
12Lane closure(setup & rem)(typ 9) (790-7009)EACH1$800.00$500.00$100.00$500.00$1,080.00$850.00$1,950.00
13Lane closure(setup & rem)(typ 10) (790-7010)EACH1$800.00$500.00$100.00$700.00$1,400.00$900.00$1,950.00
14Lane closure(setup & rem)(typ 11) (790-7011)EACH30$250.00$100.00$100.00$700.00$300.00$275.00$900.00
15Lane closure(setup & rem)(typ 13) (790-7013)EACH1$2,000.00$500.00$100.00$2,000.00$2,000.00$850.00$1,950.00
16Lane closure(setup & rem)(typ 14) (790-7014)EACH25$200.00$100.00$100.00$700.00$450.00$275.00$850.00
17Lane closure(setup & rem)(typ 15) (790-7015)EACH5$200.00$500.00$100.00$1,000.00$650.00$300.00$700.00
18Lane closure(setup & rem)(typ 16) (790-7016)EACH5$250.00$500.00$100.00$1,000.00$375.00$300.00$1,000.00
19Lane closure(setup & rem)(typ 17) (790-7017)EACH5$400.00$500.00$100.00$1,000.00$650.00$300.00$700.00
20Lane closure(setup & rem)(typ 19) (790-7019)EACH20$200.00$100.00$100.00$700.00$275.00$275.00$500.00
21Lane closure(maintenance)(typ 1) (790-7020)HR15$85.00$20.00$75.00$75.00$150.00$135.00$25.00
22Lane closure(maintenance)(typ 2) (790-7021)HR15$85.00$20.00$75.00$75.00$70.00$135.00$25.00
23Lane closure(maintenance)(typ 5) (790-7024)HR15$85.00$20.00$75.00$80.00$70.00$135.00$25.00
24Lane closure(maintenance)(typ 6) (790-7025)HR40$100.00$20.00$75.00$150.00$90.00$140.00$100.00
25Lane closure(maintenance)(typ 7) (790-7026)HR100$90.00$20.00$75.00$100.00$75.00$200.00$100.00
26Lane closure(maintenance)(typ 8) (790-7027)HR40$100.00$20.00$75.00$50.00$90.00$200.00$25.00
27Lane closure(maintenance)(typ 9) (790-7028)HR5$150.00$20.00$75.00$50.00$110.00$225.00$25.00
28Lane closure(maintenance)(typ 10) (790-7029)HR5$200.00$20.00$75.00$150.00$130.00$225.00$25.00
29Lane closure(maintenance)(typ 11) (790-7030)HR150$85.00$20.00$75.00$150.00$69.00$145.00$100.00
30Lane closure(maintenance)(typ 13) (790-7032)HR5$200.00$20.00$75.00$150.00$185.00$225.00$25.00
31Lane closure(maintenance)(typ 14) (790-7033)HR200$80.00$20.00$75.00$150.00$75.00$140.00$100.00
32Lane closure(maintenance)(typ 15) (790-7034)HR25$120.00$20.00$75.00$150.00$90.00$150.00$25.00
33Lane closure(maintenance)(typ 16) (790-7035)HR25$150.00$20.00$75.00$150.00$71.00$150.00$25.00
34Lane closure(maintenance)(typ 17) (790-7036)HR25$200.00$20.00$75.00$150.00$90.00$150.00$25.00
35Lane closure(maintenance)(typ 19) (790-7038)HR100$80.00$20.00$75.00$150.00$69.00$130.00$15.00
TxDOT contract A00212747: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of November 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy