TxDOT contract A00215343 bid tabulation
INSTALLATION OF TRAFFIC SIGNALS, US0059 (District Wide to .). Let by Texas DOT on August 26, 2025, Victoria, Yoakum District. 2 bids received; low bid $543,050 by Vaca Underground Utilities Inc, -6.6% against the engineer's estimate of $581,330.
- Owner
- Texas DOT
- Letting
- 26 AUG 2025
- Pay items
- 41
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Vaca Underground Utilities Inc | $543,050 | Low | -7.0% |
| 2 | Third Coast Services LLC | $666,570 | +23% | +15% |
Engineer's estimate: $581,330.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Vaca Underground Utilities Inc | 2. Third Coast Services LLC |
|---|---|---|---|---|---|---|
| 1 | Mobilization (callout) (500-7002) | EACH | 4 | $7,000.00 | $8,000.00 | $3,730.86 |
| 2 | Mobilization (emergency) (500-7033) | EACH | 4 | $10,000 | $4,000.00 | $3,730.86 |
| 3 | TMA (stationary) (505-7001) | DAY | 10 | $250.00 | $200.00 | $1,640.71 |
| 4 | TMA (mobile operation) (505-7003) | DAY | 10 | $300.00 | $200.00 | $2,958.77 |
| 5 | Electrical conductor (no.8) bare (620-7007) | LF | 500 | $4.00 | $2.50 | $2.52 |
| 6 | Electrical conductor (no.8) insulated (620-7008) | LF | 500 | $4.00 | $2.50 | $2.72 |
| 7 | Aluminum signs (type A) (636-7001) | SF | 320 | $50.00 | $35.00 | $40.72 |
| 8 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 300 | $5.00 | $3.50 | $4.75 |
| 9 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 300 | $5.60 | $3.00 | $5.24 |
| 10 | Install of conduit by trenching (690-7002) | LF | 500 | $12.00 | $12.00 | $36.76 |
| 11 | Install of conduit by boring (690-7004) | LF | 500 | $18.00 | $20.00 | $43.95 |
| 12 | Install of cables (690-7011) | LF | 300 | $7.00 | $6.00 | $18.90 |
| 13 | Removal of span cable assembly (690-7016) | LF | 300 | $3.00 | $100.00 | $12.44 |
| 14 | Install of span cable assembly (690-7018) | LF | 300 | $6.00 | $100.00 | $15.92 |
| 15 | Install of electrical service (690-7020) | EACH | 15 | $10,000 | $6,500.00 | $8,893.18 |
| 16 | Removal of timber poles (690-7021) | EACH | 5 | $200.00 | $500.00 | $746.18 |
| 17 | Install of timber poles (690-7023) | EACH | 5 | $2,500.00 | $500.00 | $932.72 |
| 18 | Removal of signal head assembly (690-7024) | EACH | 10 | $150.00 | $100.00 | $373.09 |
| 19 | Install of signal related signs (690-7029) | EACH | 30 | $500.00 | $450.00 | $515.64 |
| 20 | Install of control cabinet(GRND MNT) (690-7040) | EACH | 4 | $5,000.00 | $2,500.00 | $3,730.86 |
| 21 | Install of control cabinet(pole MNT) (690-7043) | EACH | 2 | $3,000.00 | $2,500.00 | $3,730.87 |
| 22 | Install of flasher cabinet (690-7046) | EACH | 4 | $2,500.00 | $1,500.00 | $4,704.71 |
| 23 | Install of RDSD FLSH beacon assembly (690-7050) | EACH | 20 | $5,000.00 | $7,500.00 | $6,875.21 |
| 24 | Removal of signal pole assembly (690-7051) | EACH | 4 | $2,200.00 | $1,500.00 | $7,461.73 |
| 25 | Install of signal pole assembly (690-7053) | EACH | 4 | $3,900.00 | $2,000.00 | $3,730.86 |
| 26 | Install of luminaire head (690-7066) | EACH | 10 | $300.00 | $600.00 | $373.09 |
| 27 | Install of luminaire mast arms (690-7069) | EACH | 10 | $250.00 | $750.00 | $746.17 |
| 28 | Ins of traffic signal PL FND (36" dril SHFT) (690-7072) | LF | 28 | $600.00 | $350.00 | $413.61 |
| 29 | Install pedestrian pole assembly (690-7087) | EACH | 4 | $1,700.00 | $1,800.00 | $1,865.44 |
| 30 | Remove pedestrian pole assembly (690-7089) | EACH | 4 | $800.00 | $500.00 | $932.72 |
| 31 | Remove traffic signal (690-7100) | EACH | 2 | $7,000.00 | $3,500.00 | $7,461.73 |
| 32 | Traffic signal HD(repl)(3SEC)(LED)W/BRKT BKPL (690-7120) | EACH | 15 | $350.00 | $200.00 | $373.09 |
| 33 | Traffic signal HD(repl)(4SEC)(LED)W/BRKT BKPL (690-7121) | EACH | 8 | $350.00 | $200.00 | $466.36 |
| 34 | Traffic signal HD(repl)(5SEC)(LED)W/BRKT BKPL (690-7122) | EACH | 8 | $350.00 | $200.00 | $559.63 |
| 35 | Install radar vehicle detection system (690-7134) | EACH | 8 | $1,500.00 | $1,000.00 | $932.72 |
| 36 | Remove radar vehicle detection system (690-7136) | EACH | 8 | $800.00 | $350.00 | $3,730.86 |
| 37 | VIVDS cable (install) (690-7137) | LF | 300 | $3.00 | $2.00 | $6.22 |
| 38 | VIVDS camera (install) (690-7138) | EACH | 8 | $1,500.00 | $750.00 | $932.72 |
| 39 | Install roadway illum assembly (LED) (690-7165) | EACH | 10 | $2,000.00 | $2,000.00 | $746.17 |
| 40 | Remove roadway illum assembly (LED) (690-7166) | EACH | 10 | $600.00 | $500.00 | $746.17 |
| 41 | Install ground box W/apron (690-7194) | EACH | 5 | $2,000.00 | $1,500.00 | $1,764.55 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 26, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way