TxDOT contract A00219572 bid tabulation
TRAFFIC SIGNAL MAINTENANCE, US0082 (Various Roadways in to Paris District). Let by Texas DOT on April 16, 2026, Lamar, Paris District. 3 bids received; low bid $549,355 by North Texas Traffic Systems Construction, -17% against the engineer's estimate of $659,279.
- Owner
- Texas DOT
- Letting
- 16 APR 2026
- Pay items
- 50
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | North Texas Traffic Systems Construction | $549,355 | Low | -17% |
| 2 | Texas Traffic Control Systems, Inc. | $612,049 | +11% | -7.0% |
| 3 | Striping Technology, L.P. | $824,039 | +50% | +25% |
Engineer's estimate: $659,279.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. North Texas Traffic Systems Construction | 2. Texas Traffic Control Systems, Inc. | 3. Striping Technology, L.P. |
|---|---|---|---|---|---|---|---|
| 1 | Riprap (concrete)(4 in) (432-7001) | CY | 6 | $591.66 | $500.00 | $550.00 | $680.00 |
| 2 | Mobilization (callout) (500-7002) | EACH | 12 | $4,500.00 | $3,200.00 | $3,500.00 | $3,500.00 |
| 3 | Temporary sediment control fence (install) (506-7039) | LF | 50 | $4.16 | $1.00 | $1.00 | $19.50 |
| 4 | Elc SRV type D 120/240 070(NS)AL(E)PS(U) (628-7168) | EACH | 3 | $7,375.80 | $5,000.00 | $5,500.00 | $9,250.00 |
| 5 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 48 | $6.89 | $15.00 | $25.00 | $20.00 |
| 6 | Eliminating existing PM & markers (24") (677-7008) | LF | 14 | $2.94 | $15.00 | $10.00 | $20.00 |
| 7 | Pavement surface preparation for marking (24") (678-7008) | LF | 48 | $0.96 | $10.00 | $8.00 | $20.00 |
| 8 | Install highway traffic signal (flash beacon) (680-7001) | EACH | 2 | $3,597.19 | $6,000.00 | $8,000.00 | $3,000.00 |
| 9 | Install highway traffic signal (isolated) (680-7002) | EACH | 4 | $13,000 | $12,500 | $15,000 | $9,500.00 |
| 10 | Install of conduit by trenching (690-7002) | LF | 2,000 | $15.59 | $10.00 | $12.00 | $20.50 |
| 11 | Install of conduit by boring (690-7004) | LF | 1,000 | $20.51 | $21.00 | $35.00 | $33.00 |
| 12 | Removal of ground boxes (690-7006) | EACH | 4 | $250.00 | $350.00 | $400.00 | $950.00 |
| 13 | Replace of ground boxes (690-7007) | EACH | 10 | $1,357.59 | $1,100.00 | $1,300.00 | $2,250.00 |
| 14 | Install of ground boxes (690-7008) | EACH | 10 | $1,171.07 | $1,100.00 | $1,500.00 | $1,950.00 |
| 15 | Removal of cables (690-7009) | LF | 6,000 | $0.89 | $2.00 | $1.50 | $3.25 |
| 16 | Install of cables (690-7011) | LF | 10,000 | $5.41 | $6.50 | $5.00 | $7.00 |
| 17 | Replace of span cable assembly (690-7017) | LF | 300 | $3.00 | $4.00 | $6.50 | $6.50 |
| 18 | Replace of electrical service (690-7019) | EACH | 2 | $3,985.77 | $1,000.00 | $5,500.00 | $10,500 |
| 19 | Install of electrical service (690-7020) | EACH | 3 | $3,313.19 | $1,000.00 | $5,500.00 | $9,250.00 |
| 20 | Removal of signal head assembly (690-7024) | EACH | 5 | $81.01 | $150.00 | $175.00 | $475.00 |
| 21 | Replace of signal head assembly (690-7025) | EACH | 50 | $954.08 | $1,250.00 | $1,250.00 | $825.00 |
| 22 | Install of signal head assembly (690-7026) | EACH | 18 | $709.57 | $1,250.00 | $1,250.00 | $825.00 |
| 23 | Removal of signal related signs (690-7027) | EACH | 5 | $76.13 | $15.00 | $150.00 | $350.00 |
| 24 | Install of signal related signs (690-7029) | EACH | 10 | $470.90 | $200.00 | $450.00 | $675.00 |
| 25 | Replace of pedestrian push buttons (690-7031) | EACH | 5 | $565.56 | $200.00 | $550.00 | $300.00 |
| 26 | Install of pedestrian push buttons (690-7032) | EACH | 5 | $407.29 | $200.00 | $550.00 | $275.00 |
| 27 | Removal of traffic signal pole FND (690-7033) | LF | 5 | $353.85 | $600.00 | $800.00 | $1,750.00 |
| 28 | Replace of control cabinet(GRND MNT) (690-7039) | EACH | 2 | $6,669.81 | $2,000.00 | $2,000.00 | $5,025.00 |
| 29 | Replace of control cabinet(pole MNT) (690-7042) | EACH | 2 | $4,239.40 | $2,000.00 | $2,000.00 | $4,500.00 |
| 30 | Replace of flasher cabinet (690-7045) | EACH | 2 | $1,500.00 | $700.00 | $2,000.00 | $625.00 |
| 31 | Removal of signal pole assembly (690-7051) | EACH | 2 | $1,776.91 | $2,000.00 | $1,750.00 | $6,250.00 |
| 32 | Replace of signal pole assembly (690-7052) | EACH | 2 | $3,678.51 | $3,500.00 | $1,750.00 | $4,650.00 |
| 33 | Install of signal pole assembly (690-7053) | EACH | 5 | $3,158.94 | $3,500.00 | $1,800.00 | $4,200.00 |
| 34 | Replace of curbs (690-7055) | LF | 50 | $25.00 | $25.00 | $50.00 | $45.00 |
| 35 | Install of pedestrian ramps (690-7059) | EACH | 1 | $4,000.00 | $800.00 | $4,500.00 | $6,250.00 |
| 36 | Replace of luminaire head (690-7065) | EACH | 10 | $752.50 | $800.00 | $750.00 | $725.00 |
| 37 | Ins of traffic signal PL FND (30" dril SHFT) (690-7071) | LF | 40 | $670.50 | $300.00 | $300.00 | $385.00 |
| 38 | Ins of traffic signal PL FND (36" dril SHFT) (690-7072) | LF | 60 | $405.65 | $360.00 | $400.00 | $425.00 |
| 39 | Ins of traffic signal PL FND (48" dril SHFT) (690-7074) | LF | 40 | $590.00 | $400.00 | $785.00 | $1,500.00 |
| 40 | Install vid image vehicle det sys (VIVDS) (690-7084) | EACH | 5 | $1,500.00 | $1,000.00 | $1,500.00 | $1,700.00 |
| 41 | Install pedestrian pole assembly (690-7087) | EACH | 5 | $1,469.31 | $2,500.00 | $2,500.00 | $2,050.50 |
| 42 | Install spread spectrum antenna (690-7098) | EACH | 2 | $150.00 | $10.00 | $1,500.00 | $1,550.00 |
| 43 | Remove traffic signal (690-7100) | EACH | 2 | $7,285.71 | $2,000.00 | $2,500.00 | $7,250.00 |
| 44 | Install bbu system (690-7131) | EACH | 2 | $2,500.00 | $1,000.00 | $7,700.00 | $10,525 |
| 45 | VIVDS camera (install) (690-7138) | EACH | 10 | $1,000.00 | $1,000.00 | $750.00 | $1,750.00 |
| 46 | VIVDS prosr sys (6006-7001) | EACH | 1 | $12,113 | $3,000.00 | $1,500.00 | $16,052 |
| 47 | VIVDS cam assy FXD LNS (6006-7002) | EACH | 4 | $4,869.69 | $1,500.00 | $1,500.00 | $3,251.00 |
| 48 | Bbu system (external battery cabinet) (6007-7001) | EACH | 2 | $8,016.09 | $7,500.00 | $9,500.00 | $10,525 |
| 49 | Video imaging and radar detector (6017-7015) | EACH | 4 | $11,288 | $5,500.00 | $1,500.00 | $6,000.00 |
| 50 | Vid image and radar det processor sys (6017-7018) | EACH | 1 | $14,399 | $12,000 | $1,500.00 | $35,675 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way