CULVERT CLEANING, FM3047 (Various Locations to Within Waco District). Let by Texas DOT on October 15, 2026, McLennan, Waco District. 2 bids received; low bid $472,690 by KriMatt Services LLC, -16% against the engineer's estimate of $561,816.

Owner
Texas DOT
Letting
15 OCT 2026
Pay items
22
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1KriMatt Services LLC$472,690Low-16%
2Skyline Construction Paving & Striping$551,544+17%-2.0%
TxDOT contract A00223243: bids by rank

Engineer's estimate: $561,816.

Bid tabulation

LinePay itemUnitQuantityEstimate1. KriMatt Services LLC2. Skyline Construction Paving & Striping
1Excavation (channel) (110-7002)CY1,235$10.63$25.00$39.97
2Broadcast seed (temporary_warm_cool) (164-7039)ACRE5$0.11$1,500.00$0.10
3Soil ret BLKT(chan_temporary_2 PSF) (169-7029)SY500$1.64$10.00$0.11
4Set (replace pipe runner assembly) (467-7003)EACH20$2,646.84$500.00$999.99
5Mobilization (callout) (500-7002)EACH8$500.00$1.00$1.00
6TMA (stationary) (505-7001)DAY40$208.78$100.00$1.00
7Rock filter dams (install) (type 1) (506-7001)LF15$35.32$30.00$1.00
8Driftwood removal (735-7060)CY2,255$94.23$65.00$79.10
9Tree trimming / brush removal(channels) (752-7003)ACRE38$1,181.52$1,800.00$300.00
10Ditch cleaning and reshaping (foot) (760-7001)LF9,125$4.85$2.75$7.59
11Drain inlet cleaning (764-7001)EACH5$105.65$150.00$99.99
12Storm sewer cleaning (pipe)(12"-18"diameter) (764-7007)LF130$1.36$2.50$6.00
13Storm sewer cleaning (pipe)(19"-24"diameter) (764-7008)LF585$3.69$4.50$6.49
14Storm sewer cleaning (pipe)(25"-30"diameter) (764-7009)LF60$3.29$5.00$7.49
15Storm sewer cleaning (pipe)(31"-36"diameter) (764-7010)LF230$5.72$6.00$8.49
16Storm sewer clean (box culvert) (6-<12 SF) (764-7016)LF680$27.12$12.50$13.81
17Storm sewer clean (box culvert)(12-<24 SF) (764-7017)LF1,630$11.77$11.00$20.81
18Storm sewer clean (box culvert)(24-<48 SF) (764-7018)LF2,291$18.84$16.00$26.13
19Storm sewer clean (box culvert)(48-<96 SF) (764-7019)LF1,720$19.33$27.00$33.33
20Storm sewer clean (box culvert) (>96 SF) (764-7020)LF900$66.80$65.00$59.01
21Slotted drain cleaning (764-7021)LF150$7.32$5.50$12.92
22Maintenance speed limit signing (7010-7002)DAY5$155.14$110.00$1.00
TxDOT contract A00223243: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of October 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy