TxDOT letting results, May 7, 2025
8 contracts let by Texas DOT on May 7, 2025, $2,873,442 in low bids, a median of 4.5 bidders per contract. On the 8 with an engineer's estimate, the low bid came in under it 6 times; median low bid -23% against the estimate.
- Owner
- Texas DOT
- Contracts
- 8
- Low bids, total
- $2,873,442
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| A00214386 | FLEXIBLE PAVEMENT STRUCTURE REPAIR, SH0031 (Various Roadways in the to Navarro County Maintenance Section) | Dallas District | 4 | Texas Materials Group, Inc. | $924,038 | $1,028,776 | +11% | +10% | TxDOT |
| A00213486 | METAL BEAM GUARD FENCE REPAIR, US0075 (VARIOUS LOCATIONS IN THE COLLIN to COUNTY MAINTENANCE SECTION) | Dallas District | 4 | Fireman Excavating, Inc. | $596,312 | $611,318 | +3.0% | -40% | TxDOT |
| A00211523 | CABLE BARRIER REPAIR, IH0045 (Various Roadways in the to Ellis County Maintenance Section) | Dallas District | 5 | Fireman Excavating, Inc. | $557,450 | $588,070 | +5.0% | -27% | TxDOT |
| A00214533 | MOWING HIGHWAY RIGHT OF WAY, SH0034 (Various Roadways in the to Ellis County Maintenance Section) | Dallas District | 6 | Cen-Tex Irrigation Systems, Inc. | $336,673 | $341,640 | +1.0% | -36% | TxDOT |
| A00211542 | REFLECTORIZED PAVEMENT MARKINGS & MARKERS, US0077 (Various Roadways in the to Ellis County Maintenance Section) | Dallas District | 8 | TRP Infrastructure Services, LLC | $186,910 | $192,989 | +3.0% | -33% | TxDOT |
| A00214367 | LIMESTONE ROCK ASPHALT, SH0005 (Collin County to Maintenance Section) | Dallas District | 2 | Martin Marietta Materials, Inc. | $150,510 | $164,980 | +10% | +28% | TxDOT |
| A00212642 | TREE TRIMMING AND BRUSH REMOVAL, US0075 (VARIOUS ROADWAYS IN THE COLLIN to COUNTY MAINTENANCE SECTION) | Dallas District | 7 | Icos Management, LLC | $79,789 | $101,585 | +27% | -18% | TxDOT |
| A00214357 | CUTBACK, SH0005 (Collin County to Maintenance Section) | Dallas District | 2 | Wright Asphalt Products Company LLC | $41,760 | $43,800 | +5.0% | -17% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.