Pipe underdrains (ty 6) (6") unit price, Texas
Low bidders on TxDOT contracts carried a median of $26.09 per LF for item 5566006, pipe underdrains (ty 6) (6"), from 08 APR 2020 to 02 AUG 2024, across 37 low bids. Half of all 172 bids fell between $19.26 and $37.10.
- Owner
- Texas DOT
- Item
- 5566006
- Unit
- LF
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 9 | 8 | $16.00 | 39 | $22.82 |
| 2021 | 12 | 11 | $25.00 | 67 | $24.00 |
| 2022 | 6 | 5 | $23.74 | 23 | $33.00 |
| 2023 | 6 | 6 | $36.47 | 22 | $40.00 |
| 2024 | 7 | 7 | $40.00 | 21 | $37.41 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Austin District | 12 | $15.41 | 75 | $24.38 |
| San Antonio District | 4 | $24.15 | 23 | $27.41 |
| Waco District | 3 | $40.00 | 14 | $37.82 |
| Bryan District | 3 | $26.50 | 12 | $34.23 |
| Beaumont District | 3 | $35.00 | 9 | $47.00 |
| Houston District | 3 | $37.41 | 8 | $33.20 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 25 to 489 | 9 | $40.40 |
| 500 to 1,014 | 9 | $26.00 |
| 1,051 to 3,180 | 9 | $15.00 |
| 4,307 to 29,263 | 10 | $22.52 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243202 | Houston District | 489 | $37.41 | $35.48 | $40.00 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 06 JUN 2024 | 06243218 | Waco District | 25 | $40.00 | $43.20 | $50.00 | 4 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 05 JUN 2024 | 06243003 | Pharr District | 1,436 | $60.72 | $47.86 | $32.90 | 2 | IOC COMPANY LLC | TxDOT |
| 02 MAY 2024 | 05243001 | Beaumont District | 5,269 | $35.00 | $35.00 | $20.00 | 1 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 02 MAY 2024 | 05243005 | Austin District | 1,830 | $30.00 | $33.50 | $40.00 | 2 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 02 MAY 2024 | 05243019 | Waco District | 120 | $40.40 | $46.00 | $50.00 | 6 | C. E. BARKER, LTD. | TxDOT |
| 04 APR 2024 | 04243001 | Dallas District | 19,924 | $43.60 | $32.25 | $40.00 | 2 | SEMA CONSTRUCTION, INC. | TxDOT |
| 06 DEC 2023 | 12233201 | Yoakum District | 8,319 | $26.00 | $36.30 | $26.00 | 3 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 07 SEP 2023 | 09233223 | Austin District | 389 | $100.01 | $52.23 | $30.00 | 4 | JOE BLAND CONSTRUCTION, L.P. | TxDOT |
| 03 AUG 2023 | 08233205 | Fort Worth District | 1,014 | $34.44 | $32.22 | $55.00 | 4 | SEMA CONSTRUCTION, INC. | TxDOT |
| 03 AUG 2023 | 08233274 | Tyler District | 500 | $50.00 | $55.00 | $50.00 | 3 | EAST TEXAS BRIDGE, INC. | TxDOT |
| 02 AUG 2023 | 08233039 | Bryan District | 399 | $38.50 | $40.00 | $20.00 | 3 | TI-ZACK CONCRETE, INC. | TxDOT |
| 04 MAY 2023 | 05233009 | San Antonio District | 425 | $27.00 | $37.00 | $20.00 | 5 | STERLING DELAWARE HOLDING COMPANY | TxDOT |
| 30 JUN 2022 | 06223603 | Dallas District | 5,110 | n/a | $27.91 | $27.00 | 2 | WEBBER, LLC | TxDOT |
| 02 JUN 2022 | 06223201 | Lufkin District | 1,000 | $46.70 | $46.00 | $20.00 | 5 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.