Wire fence (ty c) unit price, Texas
Low bidders on TxDOT contracts carried a median of $20.00 per LF for item 5526003, wire fence (ty c), from 06 FEB 2020 to 10 JUL 2024, across 137 low bids. Half of all 695 bids fell between $15.00 and $27.00.
- Owner
- Texas DOT
- Item
- 5526003
- Unit
- LF
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 22 | 22 | $13.75 | 129 | $15.50 |
| 2021 | 30 | 30 | $20.00 | 172 | $20.00 |
| 2022 | 29 | 29 | $20.00 | 151 | $20.00 |
| 2023 | 36 | 36 | $23.28 | 140 | $24.00 |
| 2024 | 20 | 20 | $22.50 | 103 | $22.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Lufkin District | 15 | $15.00 | 77 | $20.00 |
| Yoakum District | 12 | $18.70 | 75 | $18.00 |
| Childress District | 10 | $17.50 | 56 | $21.00 |
| Waco District | 10 | $22.50 | 54 | $20.00 |
| Tyler District | 7 | $24.00 | 51 | $20.00 |
| Atlanta District | 8 | $22.50 | 44 | $20.00 |
| Fort Worth District | 9 | $34.00 | 43 | $23.00 |
| San Antonio District | 6 | $20.00 | 43 | $20.00 |
| Austin District | 10 | $20.00 | 42 | $20.50 |
| Brownwood District | 9 | $16.00 | 36 | $20.00 |
| Abilene District | 7 | $22.00 | 30 | $20.50 |
| Bryan District | 4 | $8.69 | 21 | $10.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 25 to 138 | 34 | $27.50 |
| 140 to 400 | 34 | $20.00 |
| 416 to 963 | 34 | $20.00 |
| 970 to 18,990 | 35 | $15.90 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243211 | Childress District | 1,876 | $8.28 | $27.00 | $25.00 | 5 | C. E. BARKER, LTD. | TxDOT |
| 10 JUL 2024 | 07243224 | Childress District | 500 | $25.00 | $22.50 | $15.00 | 6 | SKYLINE BRIDGE LLC | TxDOT |
| 09 JUL 2024 | 07243015 | Yoakum District | 1,615 | $42.00 | $24.50 | $20.00 | 8 | STX CIVIL | TxDOT |
| 09 JUL 2024 | 07243025 | Childress District | 1,470 | $15.00 | $25.00 | $30.00 | 6 | SKYLINE BRIDGE LLC | TxDOT |
| 05 JUN 2024 | 06243048 | Atlanta District | 875 | $25.00 | $21.35 | $40.00 | 8 | THK CONSTRUCTION LLC | TxDOT |
| 05 JUN 2024 | 06243051 | Childress District | 2,200 | $15.00 | $20.00 | $30.00 | 6 | THK CONSTRUCTION LLC | TxDOT |
| 03 MAY 2024 | 05243215 | San Antonio District | 646 | $20.00 | $18.00 | $20.00 | 7 | RELMCO, INC. | TxDOT |
| 03 MAY 2024 | 05243221 | Lufkin District | 642 | $15.00 | $20.71 | $20.00 | 4 | DCC CONSTRUCTION AND SERVICES, L.L.C. | TxDOT |
| 03 MAY 2024 | 05243223 | Waco District | 66 | $95.00 | $50.00 | $29.00 | 5 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 03 MAY 2024 | 05243236 | Atlanta District | 448 | $27.00 | $19.38 | $40.00 | 4 | EAST TEXAS BRIDGE, INC. | TxDOT |
| 02 MAY 2024 | 05243019 | Waco District | 265 | $50.50 | $26.50 | $29.00 | 6 | C. E. BARKER, LTD. | TxDOT |
| 02 MAY 2024 | 05243041 | Lufkin District | 300 | $34.53 | $30.00 | $25.00 | 5 | TALBERT COMPANIES LLC | TxDOT |
| 05 APR 2024 | 04243202 | Wichita Falls District | 9,000 | $9.00 | $9.00 | $25.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 06 MAR 2024 | 03243211 | Brownwood District | 1,530 | $20.00 | $20.00 | $25.00 | 3 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 06 MAR 2024 | 03243222 | Atlanta District | 760 | $20.00 | $20.50 | $35.00 | 4 | THK CONSTRUCTION LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.