Wire fence (ty a) unit price, Texas
Low bidders on TxDOT contracts carried a median of $16.52 per LF for item 5526001, wire fence (ty a), from 06 FEB 2020 to 10 JUL 2024, across 103 low bids. Half of all 529 bids fell between $14.30 and $25.00.
- Owner
- Texas DOT
- Item
- 5526001
- Unit
- LF
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 18 | 18 | $13.46 | 117 | $15.50 |
| 2021 | 26 | 26 | $15.00 | 156 | $15.00 |
| 2022 | 21 | 21 | $16.00 | 94 | $20.00 |
| 2023 | 17 | 17 | $25.00 | 66 | $25.00 |
| 2024 | 21 | 21 | $20.00 | 96 | $23.34 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Yoakum District | 34 | $15.07 | 184 | $18.10 |
| Bryan District | 9 | $24.00 | 53 | $22.37 |
| Austin District | 5 | $10.00 | 37 | $15.00 |
| Lufkin District | 7 | $14.85 | 30 | $16.00 |
| Fort Worth District | 3 | $15.75 | 27 | $15.75 |
| Corpus Christi District | 3 | $14.00 | 25 | $13.39 |
| San Antonio District | 3 | $15.86 | 25 | $20.81 |
| Abilene District | 8 | $25.00 | 23 | $30.00 |
| Brownwood District | 3 | $12.37 | 17 | $12.00 |
| Laredo District | 3 | $16.00 | 14 | $23.24 |
| Lubbock District | 3 | $15.00 | 13 | $20.00 |
| Wichita Falls District | 4 | $18.50 | 13 | $25.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 10 to 148 | 25 | $32.79 |
| 157 to 495 | 26 | $18.50 |
| 500 to 1,280 | 26 | $15.37 |
| 1,286 to 82,110 | 26 | $13.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243213 | Lufkin District | 20 | $100.00 | $60.00 | $25.00 | 2 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 09 JUL 2024 | 07243015 | Yoakum District | 1,602 | $42.00 | $25.00 | $15.00 | 8 | STX CIVIL | TxDOT |
| 09 JUL 2024 | 07243019 | Bryan District | 55 | $54.00 | $50.00 | $40.00 | 7 | PMCO CONSTRUCTION LLC | TxDOT |
| 06 JUN 2024 | 06243205 | Wichita Falls District | 504 | $23.00 | $25.00 | $14.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 06 JUN 2024 | 06243215 | San Antonio District | 775 | $15.86 | $43.66 | $20.00 | 8 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | TxDOT |
| 06 JUN 2024 | 06243233 | Lufkin District | 10 | $100.00 | $92.50 | $20.00 | 2 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 05 JUN 2024 | 06243006 | Brownwood District | 2,094 | $12.37 | $17.18 | $25.00 | 4 | ALLEN KELLER COMPANY | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 1,365 | $23.19 | $22.50 | $20.00 | 3 | PULICE CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243231 | Abilene District | 33 | $20.00 | $50.00 | $35.00 | 5 | DCC CONSTRUCTION AND SERVICES, L.L.C. | TxDOT |
| 02 MAY 2024 | 05243002 | Laredo District | 82,110 | $8.30 | $13.90 | $18.00 | 2 | WEBBER, LLC | TxDOT |
| 02 MAY 2024 | 05243008 | El Paso District | 12,427 | $19.22 | $19.22 | $20.00 | 1 | VEMAC, LLC | TxDOT |
| 02 MAY 2024 | 05243030 | Yoakum District | 660 | $16.69 | $20.00 | $20.00 | 6 | C. E. BARKER, LTD. | TxDOT |
| 04 APR 2024 | 04243031 | Yoakum District | 157 | $21.52 | $26.40 | $20.00 | 10 | C. E. BARKER, LTD. | TxDOT |
| 06 MAR 2024 | 03243210 | Dallas District | 877.60 | $20.00 | $20.00 | $30.00 | 5 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 06 MAR 2024 | 03243211 | Brownwood District | 1,200 | $20.00 | $20.00 | $25.00 | 3 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.