Low bidders on TxDOT contracts carried a median of $759.00 per CY for item 432-7012, riprap (conc)(flume), over the 24 months to 19 NOV 2026, across 51 low bids. Half of all 312 bids fell between $642.28 and $1,000.00.
- Owner
- Texas DOT
- Item
- 432-7012
- Unit
- CY
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 2 | 2 | $699.50 | 9 | $809.00 |
| 2025 | 23 | 23 | $800.00 | 142 | $850.00 |
| 2026 | 27 | 27 | $648.28 | 166 | $750.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 6 | $624.14 | 43 | $731.00 |
| Wichita Falls District | 4 | $642.50 | 42 | $761.88 |
| Dallas District | 8 | $674.50 | 38 | $818.50 |
| Fort Worth District | 5 | $560.00 | 26 | $753.40 |
| Lubbock District | 4 | $806.12 | 25 | $926.14 |
| Amarillo District | 4 | $825.00 | 22 | $858.94 |
| Pharr District | 3 | $1,800.00 | 16 | $773.53 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 6 | 12 | $1,000.00 |
| 6 to 19.50 | 13 | $800.00 |
| 20 to 85 | 13 | $700.00 |
| 109 to 534 | 13 | $650.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00212892 | Dallas District | 298 | $520.00 | $610.80 | $900.00 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 07 OCT 2026 | A00218294 | Fort Worth District | 283.14 | $350.00 | $690.00 | $570.00 | 6 | SHALOM SERVICES CORPORATION | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 69 | $471.47 | $678.66 | $1,400.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00184830 | Amarillo District | 36 | $800.00 | $890.00 | $860.00 | 7 | GILVIN-TERRILL, LTD. | TxDOT |
| 06 AUG 2026 | A00062075 | Fort Worth District | 159 | $530.00 | $661.50 | $750.00 | 7 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 06 AUG 2026 | A00119935 | Laredo District | 35 | $624.92 | $869.36 | $732.00 | 4 | PULICE CONSTRUCTION, INC. | TxDOT |
| 05 AUG 2026 | A00128458 | Amarillo District | 40 | $950.00 | $739.15 | $750.00 | 4 | J. LEE MILLIGAN, INC. | TxDOT |
| 05 AUG 2026 | A00191471 | Houston District | 239 | $648.28 | $605.00 | $600.00 | 8 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 02 JUL 2026 | A00213157 | Wichita Falls District | 40 | $735.00 | $739.04 | $760.00 | 10 | ICOS MANAGEMENT, LLC | TxDOT |
| 02 JUL 2026 | A00124174 | Lubbock District | 20 | $650.00 | $714.09 | $600.00 | 4 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 01 JUL 2026 | A00190685 | Houston District | 72.80 | $800.00 | $696.11 | $600.00 | 11 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 01 JUL 2026 | A00219976 | Yoakum District | 6 | $600.00 | $778.31 | $800.00 | 10 | TEXAS STEEL INDUSTRIAL PLACING, LLC | TxDOT |
| 01 JUL 2026 | A00008199 | Fort Worth District | 259 | $560.00 | $567.00 | $650.00 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 01 JUL 2026 | A00218045 | Fort Worth District | 6 | $815.00 | $1,200.00 | $510.00 | 3 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 03 JUN 2026 | A00063871 | El Paso District | 495 | $535.00 | $642.50 | $800.00 | 4 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.