Riprap (stone protection)(12 in) unit price, Texas
Low bidders on TxDOT contracts carried a median of $200.00 per CY for item 432-7041, riprap (stone protection)(12 in), over the 24 months to 19 NOV 2026, across 160 low bids. Half of all 1,098 bids fell between $180.00 and $293.76.
- Owner
- Texas DOT
- Item
- 432-7041
- Unit
- CY
- Latest letting
- 12 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 7 | 7 | $225.00 | 43 | $250.00 |
| 2025 | 83 | 83 | $221.65 | 560 | $230.00 |
| 2026 | 75 | 75 | $195.00 | 525 | $220.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 35 | $220.00 | 233 | $200.00 |
| Yoakum District | 14 | $214.62 | 94 | $247.50 |
| Wichita Falls District | 12 | $200.00 | 82 | $226.50 |
| Paris District | 12 | $205.00 | 79 | $200.00 |
| Abilene District | 7 | $175.00 | 62 | $227.50 |
| Waco District | 8 | $165.00 | 59 | $200.00 |
| Corpus Christi District | 6 | $195.00 | 47 | $225.00 |
| Bryan District | 6 | $196.00 | 46 | $229.00 |
| Pharr District | 10 | $245.00 | 44 | $260.32 |
| Atlanta District | 7 | $180.00 | 41 | $205.00 |
| Austin District | 5 | $188.20 | 39 | $244.00 |
| San Antonio District | 5 | $197.00 | 39 | $225.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 48 | 40 | $282.50 |
| 52 to 170 | 40 | $201.12 |
| 172 to 461 | 40 | $200.00 |
| 474 to 12,465.60 | 40 | $169.70 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | A00219681 | Dallas District | 22 | $250.00 | $262.50 | $190.00 | 6 | ROAD DOCTORS LLC | TxDOT |
| 04 NOV 2026 | A00212892 | Dallas District | 12,465.60 | $100.00 | $163.41 | $125.00 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 04 NOV 2026 | A00209149 | Laredo District | 1,052 | $142.96 | $205.00 | $170.00 | 7 | STX CIVIL | TxDOT |
| 03 NOV 2026 | A00211095 | Odessa District | 1 | $2,000.00 | $2,000.00 | $616.20 | 7 | THE TRUESDELL CORPORATION | TxDOT |
| 07 OCT 2026 | A00209154 | Laredo District | 48 | $250.00 | $305.12 | $350.00 | 6 | PRESIDIO CONTRACTING, LLC | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 2,024 | $35.00 | $219.63 | $319.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 OCT 2026 | A00195149 | Corpus Christi District | 17.03 | $400.00 | $400.00 | $175.00 | 7 | CK NEWBERRY, LLC | TxDOT |
| 06 OCT 2026 | A00066946 | Dallas District | 601 | $273.20 | $274.10 | $300.00 | 8 | A. K. GILLIS & SONS, LLC | TxDOT |
| 06 OCT 2026 | A00207643 | Paris District | 177 | $150.00 | $165.00 | $255.00 | 7 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 09 SEP 2026 | A00218652 | Dallas District | 10 | $200.00 | $275.00 | $250.00 | 5 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 09 SEP 2026 | A00219985 | Dallas District | 318 | $175.00 | $180.00 | $154.00 | 3 | TEXAS ROAD CONSTRUCTION, LLC | TxDOT |
| 03 SEP 2026 | A00196194 | Atlanta District | 4 | $370.00 | $470.00 | $200.00 | 4 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 02 SEP 2026 | A00206056 | Wichita Falls District | 5 | $300.00 | $400.00 | $250.00 | 7 | TIGHT LINE CONSTRUCTION, LLC | TxDOT |
| 06 AUG 2026 | A00197439 | Austin District | 136 | $175.49 | $200.00 | $200.00 | 7 | STX CIVIL | TxDOT |
| 06 AUG 2026 | A00191470 | Houston District | 235 | $230.59 | $225.00 | $250.00 | 9 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.