Riprap (stone protection)(24 in) unit price, Texas
Low bidders on TxDOT contracts carried a median of $200.00 per CY for item 432-7045, riprap (stone protection)(24 in), over the 24 months to 19 NOV 2026, across 112 low bids. Half of all 856 bids fell between $190.00 and $281.95.
- Owner
- Texas DOT
- Item
- 432-7045
- Unit
- CY
- Latest letting
- 12 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 4 | 4 | $197.83 | 29 | $275.00 |
| 2025 | 59 | 59 | $210.00 | 438 | $235.00 |
| 2026 | 53 | 53 | $185.00 | 418 | $215.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Fort Worth District | 19 | $180.00 | 132 | $190.00 |
| Austin District | 10 | $225.00 | 111 | $250.00 |
| Tyler District | 15 | $200.00 | 108 | $229.65 |
| Dallas District | 12 | $185.00 | 80 | $203.50 |
| Lufkin District | 11 | $208.00 | 78 | $225.00 |
| Childress District | 6 | $210.00 | 49 | $250.00 |
| Paris District | 6 | $192.50 | 49 | $189.00 |
| Waco District | 6 | $192.50 | 49 | $200.00 |
| Brownwood District | 5 | $275.00 | 47 | $275.00 |
| San Antonio District | 3 | $225.00 | 26 | $222.03 |
| Houston District | 3 | $200.00 | 26 | $275.00 |
| Corpus Christi District | 3 | $185.00 | 23 | $228.75 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 9 to 184 | 28 | $241.68 |
| 199 to 437 | 28 | $205.00 |
| 451.11 to 1,239 | 28 | $185.00 |
| 1,266 to 31,212 | 28 | $185.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | A00219681 | Dallas District | 1,231 | $180.00 | $245.00 | $200.00 | 6 | ROAD DOCTORS LLC | TxDOT |
| 28 OCT 2026 | A00223651 | Lufkin District | 1,490 | $232.00 | $228.50 | $250.00 | 8 | BLACKSMITH VENTURES LLC | TxDOT |
| 15 OCT 2026 | A00223685 | Paris District | 340 | $245.00 | $300.00 | $325.00 | 11 | 12TWELVE ROAD AND BRIDGE LLC | TxDOT |
| 14 OCT 2026 | A00215965 | Dallas District | 143 | $200.00 | $297.50 | $210.00 | 6 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 07 OCT 2026 | A00132124 | Lufkin District | 3,010 | $185.00 | $185.00 | $180.00 | 7 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 07 OCT 2026 | A00222466 | Brownwood District | 100 | $275.00 | $275.00 | $200.00 | 9 | TAYLOR BRIDGE LLC | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 312 | $45.00 | $223.60 | $315.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 OCT 2026 | A00220460 | Brownwood District | 50 | $325.00 | $300.00 | $200.00 | 11 | TAYLOR BRIDGE LLC | TxDOT |
| 03 SEP 2026 | A00207389 | Childress District | 594 | $210.00 | $225.00 | $210.00 | 7 | COPPELL CONSTRUCTION CO., INC. | TxDOT |
| 02 SEP 2026 | A00195348 | Paris District | 1,500 | $150.00 | $156.00 | $150.00 | 7 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 06 AUG 2026 | A00192187 | Beaumont District | 1,239 | $220.00 | $222.50 | $185.00 | 6 | CASTILLO ARANDA LLC | TxDOT |
| 06 AUG 2026 | A00214454 | Fort Worth District | 320 | $180.00 | $180.00 | $196.00 | 8 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 06 AUG 2026 | A00194392 | Lufkin District | 2,246 | $160.00 | $180.00 | $150.00 | 6 | THK CONSTRUCTION LLC | TxDOT |
| 05 AUG 2026 | A00132718 | Fort Worth District | 1,266 | $135.00 | $160.00 | $150.00 | 8 | FOUTSCO PAVING COMPANY, LLC | TxDOT |
| 05 AUG 2026 | A00007222 | Fort Worth District | 692 | $120.00 | $171.71 | n/a | 11 | INDUS ROAD & BRIDGE, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way