Riprap (stone common)(dry)(18 in) unit price, Texas

Low bidders on TxDOT contracts carried a median of $210.00 per CY for item 432-7033, riprap (stone common)(dry)(18 in), over the 24 months to 19 NOV 2026, across 45 low bids. Half of all 278 bids fell between $190.50 and $323.75.

Owner
Texas DOT
Item
432-7033
Unit
CY
Latest letting
12 NOV 2026
$210.00Low bidder's median, per CY
$250.00Median of all bids, per CY
45Contracts in the window
$250.00Engineer's estimate, median per CY

By year of letting

Riprap (stone common)(dry)(18 in), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202422$280.0014$362.50
20252626$215.68162$230.00
20261818$216.00108$264.69
Riprap (stone common)(dry)(18 in), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Riprap (stone common)(dry)(18 in), TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Dallas District11$200.0069$250.00
Tyler District4$200.0030$217.50
Houston District4$189.0027$225.00
San Antonio District4$200.6821$237.00
Bryan District3$225.0018$220.00
Wichita Falls District3$200.0016$262.50
Riprap (stone common)(dry)(18 in), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Riprap (stone common)(dry)(18 in), TxDOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
3 to 24.3011$250.00
27 to 6211$222.00
63 to 14311$250.00
150 to 3,17512$180.00
Riprap (stone common)(dry)(18 in), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Riprap (stone common)(dry)(18 in)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
12 NOV 2026A00222854Amarillo District27$264.38$300.00$350.007TI-ZACK CONCRETE, LLCTxDOT
14 OCT 2026A00222907Dallas District150$180.00$300.00$180.004JACKSON EXCAVATION, LLCTxDOT
06 OCT 2026A00186301Waco District10$250.00$251.17$200.006BIG CREEK CONSTRUCTION, LTD.TxDOT
06 OCT 2026A00220834Laredo District128$325.00$462.50$265.008TAYLOR BRIDGE LLCTxDOT
06 AUG 2026A00191470Houston District29.40$317.71$246.00n/a9JAMES CONSTRUCTION GROUP, LLCTxDOT
06 AUG 2026A00219498Wichita Falls District23$200.00$250.00$250.003GARRET SHIELDS INFRASTRUCTURETxDOT
05 AUG 2026A00133874Dallas District7$175.00$300.00$375.007BIG CREEK CONSTRUCTION, LTD.TxDOT
01 JUL 2026A00187963Beaumont District91$265.00$265.00$200.003DURWOOD GREENE CONSTRUCTION CO.TxDOT
01 JUL 2026A00190685Houston District470$200.00$200.00$240.0011HARPER BROTHERS CONSTRUCTION LLCTxDOT
01 JUL 2026A00058522Tyler District53$235.00$230.00$200.007DRAKE COMPANIES LLCTxDOT
06 MAY 2026A00209252Beaumont District40$222.00$256.00$200.006R CONSTRUCTION CIVIL, LLCTxDOT
08 APR 2026A00211509Amarillo District19$1,000.00$508.75n/a8GILVIN-TERRILL, LTD.TxDOT
07 APR 2026A00207258Lubbock District15$1,200.00$730.00$350.002WEBBER, LLCTxDOT
18 MAR 2026A00214342San Antonio District62$125.00$172.50$250.006DIAMOND R CONTRACTING, LLCTxDOT
10 MAR 2026A00218250Houston District50$178.00$200.00$166.005ISI CONTRACTING, INC.TxDOT
Latest TxDOT contracts carrying Riprap (stone common)(dry)(18 in)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy