VDOT contract C0000128486N01 bid tabulation
On-call - guardrail replacement. Let by Virginia DOT on August 26, 2026, Salem. 3 bids received; low bid $593,953 by Makco, Incorporated.
- Owner
- Virginia DOT
- Letting
- 26 AUG 2026
- Pay items
- 57
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Makco, Incorporated | $593,953 | Low |
| 2 | Nickelston Industries, Inc. | $809,043 | +36% |
| 3 | L. S. Lee, Inc. | $845,853 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Makco, Incorporated | 2. Nickelston Industries, Inc. | 3. L. S. Lee, Inc. |
|---|---|---|---|---|---|---|
| 0001-0010 | Temp. silt fence type A (303SD20-0034) | LF | 50 | $10.00 | $10.00 | $7.00 |
| 0001-0020 | Utility test pit unpaved (303SX20-0012) | EACH | 10 | $400.00 | $600.00 | $1,000.00 |
| 0001-0030 | Aggr.base mat.TY. I no.21A or 21B (305SD20-0012) | TON | 300 | $75.00 | $80.00 | $120.00 |
| 0001-0040 | Machining shoulders (305SP20-0005) | LF | 2,500 | $5.00 | $7.00 | $15.00 |
| 0001-0050 | Remove EX. guardrail terminal (505SD20-0009) | EACH | 40 | $750.00 | $2,000.00 | $850.00 |
| 0001-0060 | Rub rail (505SD20-0010) | LF | 100 | $25.00 | $20.00 | $65.00 |
| 0001-0070 | Guardrail GR-MGS1 (505SD20-0011) | LF | 500 | $40.00 | $34.00 | $35.00 |
| 0001-0080 | Guardrail GR-MGS1A (505SD20-0012) | LF | 300 | $45.00 | $39.50 | $60.00 |
| 0001-0090 | Guardrail GR-MGS1, 9' post (505SD20-0013) | LF | 400 | $45.00 | $47.20 | $47.00 |
| 0001-0100 | Radial guardrail GR-MGS1 (505SD20-0014) | LF | 500 | $40.00 | $38.40 | $55.00 |
| 0001-0110 | Radial guardrail GR- MGS1, 9' post (505SD20-0016) | LF | 300 | $45.00 | $49.87 | $65.00 |
| 0001-0120 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 17 | $5,000.00 | $5,260.00 | $6,200.00 |
| 0001-0130 | Guardrail end anchorage GR-MGS3 (505SD20-0018) | EACH | 10 | $1,500.00 | $1,294.72 | $2,500.00 |
| 0001-0140 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 10 | $1,500.00 | $2,637.49 | $1,600.00 |
| 0001-0150 | Guardrail terminal GR-6 NCHRP 350 (505SD20-0027) | LF | 25 | $160.00 | $300.00 | $250.00 |
| 0001-0160 | Guardrail terminal GR-7 NCHRP 350 (505SD20-0028) | EACH | 2 | $4,400.00 | $5,000.00 | $6,000.00 |
| 0001-0170 | Guardrail terminal GR-11 (505SD20-0029) | EACH | 2 | $1,500.00 | $1,000.00 | $2,500.00 |
| 0001-0180 | Guardrail GR-2 (505SD20-0030) | LF | 300 | $40.00 | $30.00 | $35.00 |
| 0001-0190 | Guardrail GR-2 8' post (505SD20-0032) | LF | 200 | $45.00 | $38.00 | $45.00 |
| 0001-0200 | Guardrail GR-2A (505SD20-0033) | LF | 25 | $45.00 | $48.00 | $55.00 |
| 0001-0210 | Rad. guardrail GR-2A (505SD20-0035) | LF | 200 | $45.00 | $56.00 | $70.00 |
| 0001-0220 | Alt.breakaway cable term. GR-9 (505SD20-0038) | EACH | 1 | $5,000.00 | $5,000.00 | $6,200.00 |
| 0001-0230 | Guardrail GR-10 (505SD20-0040) | LF | 100 | $45.00 | $48.00 | $75.00 |
| 0001-0240 | Fixed object attach. GR- foa-1 TY. I (505SD20-0045) | EACH | 6 | $3,000.00 | $3,500.00 | $4,500.00 |
| 0001-0250 | Fixed object attach. GR- foa-1 TY. II (505SD20-0046) | EACH | 4 | $600.00 | $2,500.00 | $1,200.00 |
| 0001-0260 | Fixed object attach. GR- foa-3 TY. I (505SD20-0047) | EACH | 4 | $3,000.00 | $3,500.00 | $4,500.00 |
| 0001-0270 | Fixed object attach. GR- foa-3 TY.II (505SD20-0048) | EACH | 4 | $600.00 | $2,500.00 | $1,200.00 |
| 0001-0280 | Fixed object attach. GR- foa-4 TY. I (505SD20-0050) | EACH | 4 | $3,500.00 | $6,000.00 | $9,500.00 |
| 0001-0290 | Fixed object attach. GR- foa-4 TY. III (505SD20-0052) | EACH | 4 | $1,000.00 | $6,500.00 | $2,000.00 |
| 0001-0300 | Fixed object attach. GR- foa-2 TY. I (505SD20-0053) | EACH | 2 | $3,000.00 | $4,000.00 | $4,500.00 |
| 0001-0310 | Fixed object attach. GR- foa-2 TY. II (505SD20-0054) | EACH | 4 | $600.00 | $3,500.00 | $1,200.00 |
| 0001-0320 | Fixed object attach. GR- foa-5 (505SD20-0055) | EACH | 5 | $4,000.00 | $5,000.00 | $5,200.00 |
| 0001-0330 | Median barrier MB-3 (505SD20-0059) | LF | 150 | $60.00 | $74.00 | $85.00 |
| 0001-0340 | Guardrail beam (505SD20-0071) | LF | 300 | $30.00 | $36.50 | $65.00 |
| 0001-0350 | Remove existing guardrail (505SD20-0073) | LF | 1,500 | $10.00 | $4.50 | $10.00 |
| 0001-0360 | Offset block (505SP20-0012) | EACH | 120 | $25.00 | $20.00 | $35.00 |
| 0001-0370 | NS hand dig guardrail post hole (505SX20-0001) | EACH | 50 | $250.00 | $600.00 | $550.00 |
| 0001-0380 | NS hand dig guardrail post leave out (505SX20-0001) | EACH | 50 | $150.00 | $100.00 | $350.00 |
| 0001-0390 | NS SP. des. GR.BR.attach BR-GR type 1 or type 2 (505SX20-0044) | EACH | 3 | $5,000.00 | $10,000 | $12,000 |
| 0001-0400 | NS guardrail guardrail ter.site preparation 4' moderate (505SX20-0058) | EACH | 15 | $1,000.00 | $1,800.00 | $900.00 |
| 0001-0410 | NS guardrail guardrail ter.site preparation 6' moderate (505SX20-0058) | EACH | 15 | $1,000.00 | $2,000.00 | $900.00 |
| 0001-0420 | NS guardrail guardrail ter.site preparation minor (505SX20-0058) | EACH | 20 | $1,000.00 | $1,500.00 | $900.00 |
| 0001-0430 | Truck mounted attenuator (512SD20-0023) | HR | 100 | $50.00 | $25.00 | $0.01 |
| 0001-0440 | Group 2 channelizing devices (512SD20-0024) | DAY | 2,000 | $1.00 | $0.01 | $0.01 |
| 0001-0450 | Electronic arrow board (512SD20-0026) | HR | 1,700 | $1.00 | $20.00 | $0.01 |
| 0001-0460 | Flagger service (512SD20-0027) | HR | 200 | $35.00 | $40.00 | $45.00 |
| 0001-0470 | Impact attenuator IA-1 (512SD20-0069) | EACH | 1 | $45,000 | $10,000 | $42,000 |
| 0001-0480 | Portable temporary rumble strip array (512SP20-0001) | DAY | 25 | $100.00 | $500.00 | $600.00 |
| 0001-0490 | NS mobilization on-call task order - bedford residency (greater than $75,000) (513SX20-0001) | EACH | 1 | $1.00 | $500.00 | $1,500.00 |
| 0001-0500 | NS mobilization on-call task order - bedford residency (less than $75,000) (513SX20-0001) | EACH | 1 | $1.00 | $2,000.00 | $3,000.00 |
| 0001-0510 | NS mobilization on-call task order - christiansburg residency (greater than $75,000) (513SX20-0001) | EACH | 1 | $1.00 | $500.00 | $1,500.00 |
| 0001-0520 | NS mobilization on-call task order - christiansburg residency (less than $75,000) (513SX20-0001) | EACH | 1 | $1.00 | $2,000.00 | $3,000.00 |
| 0001-0530 | NS mobilization on-call task order - martinsville residency (greater than $75,000) (513SX20-0001) | EACH | 1 | $1.00 | $100.00 | $1,500.00 |
| 0001-0540 | NS mobilization on-call task order - martinsville residency (less than $75,000) (513SX20-0001) | EACH | 1 | $1.00 | $200.00 | $3,000.00 |
| 0001-0550 | NS mobilization on-call task order - salem residency (greater than $75,000) (513SX20-0001) | EACH | 1 | $1.00 | $500.00 | $1,500.00 |
| 0001-0560 | NS mobilization on-call task order - salem residency (less than $75,000) (513SX20-0001) | EACH | 1 | $1.00 | $2,000.00 | $3,000.00 |
| 0001-0570 | Guardrail delineator (702SD20-0001) | EACH | 6 | $20.00 | $15.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of August 26, 2026. Compiled by Mirage Metrics.