Adjust catch basin unit price, Washington

Low bidders on WSDOT contracts carried a median of $425.00 per EACH for adjust catch basin, from 01 MAR 2000 to 29 MAR 2023, across 224 low bids. Half of all 909 bids fell between $300.00 and $600.00.

Owner
Washington State DOT
Item
No code published
Unit
EACH
Latest letting
29 MAR 2023
$425.00Low bidder's median, per EACH
$425.00Median of all bids, per EACH
225Contracts in the window
$450.00Engineer's estimate, median per EACH

By year of letting

Adjust catch basin, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20001010$250.0036$290.00
20011515$300.0054$300.00
200299$300.0031$300.00
20031312$287.5063$325.00
20041212$275.0056$360.00
20051717$400.0058$400.00
20061010$446.0035$392.00
20071717$400.0072$450.00
20081010$430.0041$465.00
20091313$450.0072$400.00
20101111$400.0066$400.00
20111010$425.0059$400.00
201255$450.0027$450.00
201366$457.5022$457.50
201477$600.0022$600.00
201599$675.0028$600.00
201644$625.0016$500.00
20171010$600.0028$612.50
201877$795.0022$772.50
20191212$774.0042$800.00
202022$1,575.008$1,585.00
202144$730.0015$700.00
202244$1,270.0010$930.00
202388$690.0026$1,000.00
Adjust catch basin, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Adjust catch basin, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region100$400.00448$400.00
OR region50$400.00198$400.00
ER region30$612.50100$610.00
NCR region24$402.2573$400.00
SWR region14$375.0055$425.00
SCR region4$437.5014$500.00
Adjust catch basin, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Adjust catch basin, WSDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 256$500.00
2 to 556$402.25
5 to 1456$400.00
14 to 10456$429.12
Adjust catch basin, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Adjust catch basin
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
29 MAR 2023009941OR region3$792.50$896.25$1,000.006JOHANSEN CONSTRUCTION COMPANY,WSDOT
29 MAR 2023009954NWR region8$680.00$1,115.00$1,000.002GRANITE CONSTRUCTION COMPANYWSDOT
22 MAR 2023009950NWR region1$500.00$1,150.00$828.752COMBINED CONSTRUCTION, INC.WSDOT
01 MAR 2023009938ER region32$925.00$1,350.00$450.003CENTRAL WASHINGTON ASPHALT, INWSDOT
23 FEB 2023009925ER region2$700.00$1,100.00$900.002MAX J. KUNEY COMPANYWSDOT
23 FEB 2023009934NCR region4$900.00$770.00$500.003CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALTWSDOT
01 FEB 2023009921NCR region2$404.50$1,240.00$1,200.004JOHANSEN CONSTRUCTION COMPANY,WSDOT
25 JAN 2023009914ER region13$530.00$1,055.36$450.004POE ASPHALT PAVING, INC.WSDOT
13 APR 2022009781NWR region1$1,750.00$1,500.00$600.004TUCCI & SONS, INC.WSDOT
24 FEB 2022009767NCR region2$500.00$550.00$600.002GRANITE CONSTRUCTION COMPANYWSDOT
09 FEB 2022009765ER region1$2,000.00$1,450.00$450.002SHAMROCK PAVING, INC.WSDOT
05 JAN 2022009752NCR region2$790.00$680.00$1,000.002CENTRAL WASHINGTON ASPHALT, INWSDOT
21 APR 2021009662NWR region5$500.00$595.00$600.004SCARSELLA BROS., INC.WSDOT
24 MAR 2021009664SWR region1$860.00$860.00$1,500.003MCDONALD EXCAVATING, INC.WSDOT
24 MAR 2021009656NWR region3$600.00$650.00$850.004MARSHBANK CONSTRUCTION, INC.WSDOT
Latest WSDOT contracts carrying Adjust catch basin

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy