Adjust manhole unit price, Washington
Low bidders on WSDOT contracts carried a median of $500.00 per EACH for adjust manhole, from 01 MAR 2000 to 29 MAR 2023, across 211 low bids. Half of all 827 bids fell between $360.00 and $700.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- EACH
- Latest letting
- 29 MAR 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 11 | 11 | $250.00 | 38 | $300.00 |
| 2001 | 12 | 12 | $336.25 | 42 | $375.00 |
| 2002 | 9 | 9 | $300.00 | 33 | $300.00 |
| 2003 | 9 | 8 | $325.00 | 41 | $350.00 |
| 2004 | 9 | 9 | $370.00 | 36 | $500.00 |
| 2005 | 12 | 12 | $372.50 | 49 | $380.00 |
| 2006 | 6 | 6 | $500.00 | 21 | $400.00 |
| 2007 | 13 | 13 | $480.00 | 49 | $500.00 |
| 2008 | 7 | 7 | $460.00 | 20 | $595.00 |
| 2009 | 10 | 10 | $475.00 | 60 | $455.00 |
| 2010 | 10 | 10 | $412.50 | 58 | $475.00 |
| 2011 | 16 | 16 | $437.50 | 75 | $450.00 |
| 2012 | 7 | 7 | $382.50 | 42 | $500.00 |
| 2013 | 5 | 5 | $440.00 | 20 | $450.00 |
| 2014 | 8 | 8 | $550.00 | 28 | $630.00 |
| 2015 | 13 | 13 | $600.00 | 37 | $600.00 |
| 2016 | 7 | 7 | $800.00 | 28 | $700.00 |
| 2017 | 18 | 18 | $750.00 | 52 | $720.00 |
| 2018 | 7 | 7 | $765.00 | 21 | $880.00 |
| 2019 | 7 | 7 | $775.00 | 17 | $850.00 |
| 2020 | 4 | 4 | $687.50 | 13 | $820.00 |
| 2021 | 5 | 5 | $730.00 | 22 | $835.00 |
| 2022 | 1 | 1 | $1,450.00 | 3 | $1,118.00 |
| 2023 | 6 | 6 | $850.00 | 22 | $1,050.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 76 | $450.00 | 341 | $450.00 |
| OR region | 36 | $682.50 | 141 | $500.00 |
| NCR region | 35 | $415.00 | 104 | $487.50 |
| ER region | 29 | $550.00 | 94 | $587.50 |
| SWR region | 15 | $350.00 | 81 | $450.00 |
| SCR region | 19 | $450.00 | 61 | $550.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 52 | $500.00 |
| 2 to 4 | 53 | $500.00 |
| 5 to 15 | 53 | $472.50 |
| 16 to 267 | 53 | $475.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 29 MAR 2023 | 009941 | OR region | 7 | $1,440.00 | $1,225.00 | $1,000.00 | 6 | JOHANSEN CONSTRUCTION COMPANY, | WSDOT |
| 22 MAR 2023 | 009950 | NWR region | 1 | $500.00 | $1,150.00 | $1,049.75 | 2 | COMBINED CONSTRUCTION, INC. | WSDOT |
| 01 MAR 2023 | 009938 | ER region | 1 | $925.00 | $1,350.00 | $450.00 | 3 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 23 FEB 2023 | 009934 | NCR region | 12 | $900.00 | $770.00 | $600.00 | 3 | CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 01 FEB 2023 | 009921 | NCR region | 2 | $682.00 | $1,091.00 | $800.00 | 4 | JOHANSEN CONSTRUCTION COMPANY, | WSDOT |
| 25 JAN 2023 | 009914 | ER region | 4 | $800.00 | $1,055.36 | $450.00 | 4 | POE ASPHALT PAVING, INC. | WSDOT |
| 23 MAR 2022 | 009771 | OR region | 88 | $1,450.00 | $1,118.00 | $900.00 | 3 | TUCCI & SONS, INC. | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 13 | $1,005.00 | $875.00 | $650.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 24 MAR 2021 | 009664 | SWR region | 3 | $730.00 | $1,000.00 | $1,500.00 | 3 | MCDONALD EXCAVATING, INC. | WSDOT |
| 03 FEB 2021 | 009625 | SCR region | 6 | $600.00 | $601.00 | $800.00 | 8 | SCARSELLA BROS., INC. | WSDOT |
| 03 FEB 2021 | 009632 | SCR region | 5 | $936.40 | $1,068.20 | $750.00 | 2 | MORENO & NELSON CONSTRUCTION | WSDOT |
| 13 JAN 2021 | 009623 | ER region | 5 | $600.00 | $600.00 | $1,000.00 | 5 | MAX J. KUNEY COMPANY | WSDOT |
| 12 FEB 2020 | 009519 | SCR region | 2 | $820.00 | $850.00 | $750.00 | 3 | INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 05 FEB 2020 | 009501 | NWR region | 8 | $550.00 | $700.00 | $1,000.00 | 5 | TITAN EARTHWORK LLC | WSDOT |
| 15 JAN 2020 | 009505 | ER region | 4 | $575.00 | $2,000.00 | $1,000.00 | 3 | SHAMROCK PAVING, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.