Asphalt for fog seal unit price, Washington

Low bidders on WSDOT contracts carried a median of $650.00 per TON for asphalt for fog seal, from 21 DEC 2000 to 05 APR 2023, across 209 low bids. Half of all 621 bids fell between $500.00 and $1,100.00.

Owner
Washington State DOT
Item
No code published
Unit
TON
Latest letting
05 APR 2023
$650.00Low bidder's median, per TON
$700.00Median of all bids, per TON
214Contracts in the window
$650.00Engineer's estimate, median per TON

By year of letting

Asphalt for fog seal, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200011$230.002$205.00
200111$450.002$525.00
200244$350.008$300.00
200355$350.0013$350.00
200499$270.0025$260.00
20051010$355.0030$340.00
200677$385.0016$442.50
200799$575.0020$575.00
200877$487.0026$515.00
2009109$600.0029$750.00
20101313$600.0044$602.50
2011107$725.0035$700.00
201266$755.0023$750.00
20131211$800.0039$800.00
201477$750.0019$710.00
20151111$797.0035$845.00
20161616$612.5046$650.00
20171717$750.0041$750.00
20181616$835.0038$875.00
20191111$525.0036$897.50
202088$1,475.0026$1,200.00
202188$437.5022$635.00
202299$825.0024$1,057.50
202377$1,040.0022$1,265.00
Asphalt for fog seal, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Asphalt for fog seal, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
SCR region50$750.00163$750.00
ER region41$525.00140$592.50
NCR region51$600.00134$650.00
NWR region29$1,500.0080$1,400.00
OR region26$590.0071$700.00
SWR region12$425.0033$575.00
Asphalt for fog seal, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Asphalt for fog seal, WSDOT: low bidder's median by quantity band
Quantity (TON)Low bidsLow-bid median
0.10 to 5.9052$1,475.00
6 to 22.1552$703.50
22.80 to 11452$585.00
117 to 1,473.5053$525.00
Asphalt for fog seal, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Asphalt for fog seal
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
05 APR 2023009948SCR region2.50$1,875.00$1,500.00$4,000.003COMBINED CONSTRUCTION, INC.WSDOT
22 MAR 2023009949SCR region41.30$700.00$700.00$2,500.003CENTRAL WASHINGTON ASPHALT, INC.GRANITE CONSTRUCTION COMPANYWSDOT
08 MAR 2023009944ER region16.10$2,365.00$2,200.00$1,800.003CONSTRUCTION AHEAD, INC. DBAWSDOT
01 MAR 2023009936NCR region19$965.00$1,002.50$1,900.002CENTRAL WASHINGTON ASPHALT, INC.GRANITE CONSTRUCTION COMPANYWSDOT
23 FEB 2023009934NCR region38.20$850.00$965.00$1,100.002CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALTWSDOT
01 FEB 2023009921NCR region13.50$1,040.00$1,085.00$1,050.004JOHANSEN CONSTRUCTION COMPANY,WSDOT
25 JAN 2023009910NWR region50$1,600.00$1,600.00$1,300.005ACME CONCRETE PAVING, INC.WSDOT
13 APR 2022009796NWR region246.80$1,300.00$1,150.00$530.002GRANITE CONSTRUCTION COMPANYWSDOT
06 APR 2022009787SWR region362$300.00$635.00$400.002CENTRAL WASHINGTON ASPHALT, INWSDOT
30 MAR 2022009778NCR region188.50$800.00$1,000.00$550.003CENTRAL WASHINGTON ASPHALT, INWSDOT
23 MAR 2022009784ER region491$800.00$800.00$525.001CENTRAL WASHINGTON ASPHALT, INWSDOT
09 MAR 2022009776SCR region1.80$3,500.00$2,950.00$2,000.002CENTRAL WASHINGTON ASPHALT, INWSDOT
24 FEB 2022009768SCR region223.09$550.00$787.50$550.004DOOLITTLE CONSTRUCTION LLCWSDOT
09 FEB 2022009763OR region1.10$4,100.00$4,000.00$3,114.007KRAEMER NORTH AMERICA, LLC.WSDOT
12 JAN 2022009758NWR region5$2,900.00$2,900.00$2,000.001AWARD CONSTRUCTION, INC.WSDOT
Latest WSDOT contracts carrying Asphalt for fog seal

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.