Adjust junction box unit price, Washington
Low bidders on WSDOT contracts carried a median of $275.00 per EACH for adjust junction box, from 01 MAR 2000 to 16 MAR 2022, across 87 low bids. Half of all 318 bids fell between $200.00 and $471.25.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- EACH
- Latest letting
- 16 MAR 2022
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 4 | 4 | $85.00 | 18 | $262.50 |
| 2001 | 4 | 4 | $275.00 | 10 | $250.00 |
| 2002 | 5 | 5 | $168.00 | 19 | $200.00 |
| 2003 | 4 | 3 | $250.00 | 11 | $250.00 |
| 2004 | 4 | 4 | $300.00 | 19 | $300.00 |
| 2005 | 11 | 11 | $250.00 | 45 | $260.00 |
| 2006 | 4 | 4 | $180.00 | 13 | $250.00 |
| 2007 | 6 | 6 | $265.00 | 23 | $490.00 |
| 2008 | 7 | 7 | $300.00 | 20 | $325.00 |
| 2009 | 2 | 2 | $680.00 | 19 | $300.00 |
| 2010 | 7 | 7 | $364.00 | 29 | $300.00 |
| 2011 | 4 | 4 | $262.50 | 20 | $230.00 |
| 2013 | 2 | 2 | $287.50 | 7 | $325.00 |
| 2014 | 3 | 3 | $200.00 | 6 | $200.00 |
| 2015 | 1 | 1 | $225.00 | 2 | $237.50 |
| 2016 | 2 | 2 | $210.00 | 6 | $225.00 |
| 2017 | 6 | 6 | $360.00 | 16 | $325.00 |
| 2018 | 5 | 5 | $800.00 | 16 | $450.00 |
| 2019 | 3 | 3 | $1,200.00 | 6 | $1,200.00 |
| 2021 | 3 | 3 | $475.00 | 11 | $400.00 |
| 2022 | 1 | 1 | $600.00 | 2 | $500.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 30 | $342.50 | 121 | $310.00 |
| OR region | 29 | $270.00 | 109 | $250.00 |
| SWR region | 6 | $200.00 | 30 | $230.00 |
| ER region | 8 | $350.00 | 23 | $400.00 |
| NCR region | 6 | $187.50 | 17 | $275.00 |
| SCR region | 7 | $168.00 | 16 | $209.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 21 | $400.00 |
| 2 to 5 | 22 | $362.00 |
| 5 to 15 | 22 | $250.00 |
| 15 to 59 | 22 | $200.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 16 MAR 2022 | 009782 | Region 9 | 1 | $600.00 | $500.00 | $500.00 | 2 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 15 | $475.00 | $612.50 | $500.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 24 MAR 2021 | 009636 | OR region | 8 | $500.00 | $375.00 | $400.00 | 4 | GRAHAM CONTRACTING, LTD. | WSDOT |
| 24 MAR 2021 | 009664 | SWR region | 20 | $70.00 | $70.00 | $500.00 | 3 | MCDONALD EXCAVATING, INC. | WSDOT |
| 17 APR 2019 | 009400 | ER region | 3 | $4,235.00 | $3,117.50 | $1,000.00 | 2 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 24 JAN 2019 | 009363 | NWR region | 2 | $1,200.00 | $1,200.00 | $510.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 09 JAN 2019 | 009362 | NWR region | 16 | $1,000.00 | $825.00 | $250.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 04 APR 2018 | 009238 | SWR region | 1 | $800.00 | $500.00 | $400.00 | 3 | ROGNLIN'S, INC. | WSDOT |
| 07 MAR 2018 | 009220 | NWR region | 15 | $550.00 | $550.00 | $250.00 | 1 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 22 FEB 2018 | 009212 | NWR region | 6 | $1,000.00 | $300.00 | $600.00 | 4 | TUCCI & SONS, INC. | WSDOT |
| 14 FEB 2018 | 009182 | NWR region | 7 | $1,000.00 | $250.00 | $400.00 | 5 | TUCCI & SONS, INC. | WSDOT |
| 10 JAN 2018 | 009187 | ER region | 8 | $400.00 | $650.00 | $600.00 | 3 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 13 DEC 2017 | 009171 | OR region | 1 | $2,250.00 | $1,250.00 | $600.00 | 2 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 12 APR 2017 | 009056 | OR region | 6 | $200.00 | $250.00 | $300.00 | 3 | TUCCI & SONS, INC. | WSDOT |
| 05 APR 2017 | 009063 | ER region | 1 | $525.00 | $437.50 | $250.00 | 2 | CPM DEVELOPMENT CORPORATION | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.