Beam guardrail type thrie beam unit price, Washington
Low bidders on WSDOT contracts carried a median of $60.00 per LF for beam guardrail type thrie beam, from 14 FEB 2001 to 05 APR 2023, across 49 low bids. Half of all 167 bids fell between $43.00 and $90.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- LF
- Latest letting
- 05 APR 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2001 | 5 | 5 | $40.00 | 19 | $35.00 |
| 2002 | 2 | 2 | $59.00 | 5 | $26.00 |
| 2003 | 2 | 2 | $41.00 | 5 | $43.00 |
| 2004 | 5 | 5 | $50.00 | 15 | $50.00 |
| 2005 | 6 | 6 | $49.33 | 23 | $47.65 |
| 2006 | 4 | 4 | $74.38 | 11 | $79.05 |
| 2007 | 4 | 4 | $85.00 | 11 | $80.00 |
| 2008 | 3 | 3 | $79.80 | 6 | $79.90 |
| 2009 | 5 | 5 | $53.70 | 15 | $68.00 |
| 2010 | 3 | 3 | $41.00 | 23 | $43.00 |
| 2011 | 2 | 2 | $71.28 | 9 | $87.25 |
| 2012 | 1 | 1 | $125.00 | 4 | $125.00 |
| 2013 | 3 | 3 | $66.50 | 12 | $77.25 |
| 2019 | 3 | 3 | $140.00 | 6 | $207.50 |
| 2023 | 1 | 1 | $366.00 | 3 | $366.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 18 | $57.95 | 63 | $55.30 |
| SWR region | 8 | $56.33 | 35 | $45.00 |
| SCR region | 9 | $80.00 | 28 | $93.00 |
| OR region | 7 | $47.65 | 18 | $60.50 |
| NCR region | 4 | $57.62 | 12 | $45.00 |
| ER region | 3 | $51.00 | 11 | $57.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 12 to 185 | 12 | $85.00 |
| 200 to 387.50 | 12 | $62.15 |
| 438 to 613 | 12 | $53.38 |
| 725 to 3,666 | 13 | $53.70 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 05 APR 2023 | 009948 | SCR region | 54 | $366.00 | $366.00 | $150.00 | 3 | COMBINED CONSTRUCTION, INC. | WSDOT |
| 06 MAR 2019 | 009380 | NWR region | 56 | $386.00 | $350.00 | $150.00 | 3 | FABER CONSTRUCTION CORP. | WSDOT |
| 06 MAR 2019 | 009391 | SCR region | 525 | $140.00 | $137.50 | $150.00 | 2 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 06 FEB 2019 | 009361 | NWR region | 105 | $110.00 | $110.00 | $60.00 | 1 | C.A. CAREY CORPORATION | WSDOT |
| 27 FEB 2013 | 008419 | SCR region | 122.25 | $75.50 | $85.00 | $75.00 | 6 | PENHALL COMPANY | WSDOT |
| 16 JAN 2013 | 008405 | NWR region | 32 | $47.00 | $47.34 | $75.00 | 4 | MIDMOUNTAIN CONTRACTORS, INC. | WSDOT |
| 16 JAN 2013 | 008399 | SCR region | 382 | $66.50 | $78.25 | $80.00 | 2 | COLUMBIA ASPHALT & GRAVEL, INC | WSDOT |
| 25 APR 2012 | 008278 | SWR region | 475 | $125.00 | $125.00 | $100.00 | 4 | KERR CONTRACTORS, INC. | WSDOT |
| 26 JAN 2011 | 008076 | OR region | 288 | $87.25 | $88.00 | $80.00 | 5 | TUCCI & SONS, INC. | WSDOT |
| 05 JAN 2011 | 008052 | NWR region | 325 | $55.30 | $55.30 | $60.00 | 4 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 14 APR 2010 | 007916 | NWR region | 488 | $41.00 | $42.66 | $60.00 | 9 | VETCH CONSTRUCTION LLC | WSDOT |
| 24 MAR 2010 | 007893 | SCR region | 513 | $96.00 | $96.00 | $100.00 | 7 | GOODFELLOW BROS., INC. | WSDOT |
| 27 JAN 2010 | 007874 | NWR region | 326 | $38.40 | $40.00 | $75.00 | 7 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 16 DEC 2009 | 007860 | NWR region | 1,860 | $71.50 | $82.65 | $75.00 | 2 | PETERSEN BROTHERS, INC. | WSDOT |
| 19 MAR 2009 | 007696 | ER region | 530 | $49.00 | $63.77 | $100.00 | 4 | FRANK GURNEY, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.