Catch basin type 1 unit price, Washington

Low bidders on WSDOT contracts carried a median of $5,000.00 per EACH for catch basin type 1, over the 24 months to 07 OCT 2026, across 2 low bids. Half of all 10 bids fell between $3,150.25 and $5,350.00.

Owner
Washington State DOT
Item
No code published
Unit
EACH
Latest letting
08 JUL 2026
$5,000.00Low bidder's median, per EACH
$4,272.41Median of all bids, per EACH
2Contracts in the window
$4,500.00Engineer's estimate, median per EACH

By year of letting

Catch basin type 1, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200044$925.0024$1,000.00
200199$925.0049$900.00
200277$800.0034$900.00
200387$850.0041$950.00
20041111$900.0062$1,000.00
20051212$1,050.0061$1,000.00
200666$975.0030$1,000.00
20071212$1,105.0062$1,200.00
200844$1,255.0023$1,100.00
200987$1,150.0047$1,150.00
20101313$1,000.00112$1,000.00
201199$1,000.0062$1,000.00
201233$1,000.0022$1,200.00
201377$1,632.6137$1,500.00
201444$3,125.0029$1,500.00
201533$2,230.0018$1,875.00
201633$1,700.0020$1,850.00
201788$1,950.0035$1,600.00
201844$1,700.0010$2,050.00
201944$2,828.0014$2,578.00
202011$1,600.003$2,161.20
202188$2,000.0035$2,000.00
202255$3,200.0014$3,000.00
202344$2,762.5017$3,000.00
202622$5,000.0010$4,272.41
Catch basin type 1, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Catch basin type 1, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region84$1,055.00507$1,100.00
SWR region16$1,550.00107$1,225.00
OR region17$950.00100$947.50
NCR region19$1,364.8964$1,357.45
SCR region10$1,576.2650$1,300.00
ER region9$1,160.0036$1,497.70
Catch basin type 1, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Catch basin type 1, WSDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 239$1,650.00
2 to 539$1,364.89
5 to 1239$1,150.00
14 to 13440$1,000.00
Catch basin type 1, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Catch basin type 1
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
08 JUL 2026XE3751SCR region1$6,000.00$5,200.00$3,000.004TAPANI, INC.WSDOT
01 JUL 2026XE3756SCR region4$4,000.00$3,433.50$6,000.006N.A. DEGERSTROM, INC.WSDOT
29 MAR 2023009941OR region1$2,725.00$2,595.00$3,000.006JOHANSEN CONSTRUCTION COMPANY,WSDOT
23 FEB 2023009934NCR region2$6,500.00$3,310.00$3,000.003CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALTWSDOT
01 FEB 2023009921NCR region9$2,135.00$2,930.00$1,600.004JOHANSEN CONSTRUCTION COMPANY,WSDOT
11 JAN 2023009909SWR region1$2,800.00$3,900.00$2,500.004THOMPSON BROS. EXCAVATING, INCWSDOT
16 MAR 2022009782Region 92$5,000.00$5,200.00$2,500.002LAKESIDE INDUSTRIES, INC.WSDOT
09 MAR 2022009774OR region3$3,200.00$2,725.00$1,870.002KRAEMER NORTH AMERICA, LLC.WSDOT
24 FEB 2022009767NCR region1$3,000.00$3,000.00$2,000.002GRANITE CONSTRUCTION COMPANYWSDOT
09 FEB 2022009763OR region9$3,700.00$2,800.00$1,694.007KRAEMER NORTH AMERICA, LLC.WSDOT
12 JAN 2022009758NWR region2$2,600.00$2,600.00$2,000.001AWARD CONSTRUCTION, INC.WSDOT
15 DEC 2021009742NWR region1$2,200.00$2,850.00$2,000.004GRANITE CONSTRUCTION COMPANYWSDOT
07 APR 2021009668NWR region1$1,800.00$1,936.00$2,600.005INTERWEST CONSTRUCTION, INC.WSDOT
24 MAR 2021009636OR region5$3,000.00$3,324.42$2,000.004GRAHAM CONTRACTING, LTD.WSDOT
24 MAR 2021009664SWR region1$2,250.00$2,250.00$4,500.003MCDONALD EXCAVATING, INC.WSDOT
Latest WSDOT contracts carrying Catch basin type 1

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy