Bridge approach slab unit price, Washington

Low bidders on WSDOT contracts carried a median of $600.00 per SY for bridge approach slab, over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 6 bids fell between $600.00 and $827.00.

Owner
Washington State DOT
Item
No code published
Unit
SY
Latest letting
01 JUL 2026
$600.00Low bidder's median, per SY
$700.00Median of all bids, per SY
1Contracts in the window
$550.00Engineer's estimate, median per SY

By year of letting

Bridge approach slab, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200022$152.5015$150.00
200211$230.002$226.67
200333$200.0020$195.00
200411$150.003$165.00
200544$207.0318$205.00
200611$215.004$205.50
200777$275.0041$265.00
200866$295.0030$285.00
200954$230.0036$230.00
201088$222.5051$220.00
201155$250.0041$215.00
201233$195.0029$240.00
201344$227.6224$248.75
201422$212.5027$250.00
201522$277.509$320.00
201633$400.0020$242.50
201766$300.0028$332.50
201855$445.0023$350.00
201966$422.0038$350.00
202022$337.5012$350.00
202133$275.0018$291.90
202244$600.0015$475.00
202333$380.0012$500.00
202611$600.006$700.00
Bridge approach slab, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Bridge approach slab, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region29$250.00177$245.00
OR region17$400.0096$345.00
SCR region15$300.0091$280.00
SWR region10$232.6287$247.50
ER region11$285.0054$250.00
NCR region4$282.5017$300.00
Bridge approach slab, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Bridge approach slab, WSDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
10 to 19021$400.00
190 to 30222$300.00
304 to 68921$255.00
714 to 3,41722$222.50
Bridge approach slab, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Bridge approach slab
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
01 JUL 2026XE3756SCR region190$600.00$700.00$550.006N.A. DEGERSTROM, INC.WSDOT
12 APR 2023009945SCR region190$750.00$550.00$450.003KRAEMER NORTH AMERICA, LLC.WSDOT
23 FEB 2023009925ER region302$300.00$350.00$400.002MAX J. KUNEY COMPANYWSDOT
19 JAN 2023009891OR region350$380.00$500.00$450.007CECCANTI, INC.WSDOT
09 MAR 2022009774OR region361$450.00$462.50$400.002KRAEMER NORTH AMERICA, LLC.WSDOT
02 MAR 2022009762NWR region158$750.00$750.00$550.003MIDMOUNTAIN CONTRACTORS, INC.WSDOT
02 MAR 2022009772OR region10$1,300.00$1,410.00$550.003TUCCI & SONS, INC.WSDOT
09 FEB 2022009763OR region1,095$400.00$420.00$350.007KRAEMER NORTH AMERICA, LLC.WSDOT
07 APR 2021009668NWR region493$275.00$367.00$300.005INTERWEST CONSTRUCTION, INC.WSDOT
03 FEB 2021009625SCR region546$320.00$300.40$350.008SCARSELLA BROS., INC.WSDOT
13 JAN 2021009623ER region345$255.00$275.78$250.005MAX J. KUNEY COMPANYWSDOT
20 FEB 2020009516OR region832$350.00$362.50$350.008INTERWEST CONSTRUCTION, INC.WSDOT
23 JAN 2020009509ER region480$325.00$270.00$350.004GARCO CONSTRUCTION, INC.WSDOT
24 APR 2019009426ER region246$400.00$466.47$350.004N.A. DEGERSTROM, INC.WSDOT
10 APR 2019009419SWR region252$240.00$311.00$350.008FARLINE BRIDGE, INCORPORATEDWSDOT
Latest WSDOT contracts carrying Bridge approach slab

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way