By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2005 | 4 | 4 | $12.57 | 15 | $12.90 |
| 2006 | 1 | 1 | $12.75 | 3 | $13.00 |
| 2007 | 1 | 1 | $5.40 | 2 | $6.20 |
| 2009 | 3 | 3 | $13.35 | 15 | $13.35 |
| 2010 | 4 | 4 | $8.88 | 23 | $9.00 |
| 2013 | 1 | 1 | $10.00 | 4 | $11.50 |
| 2014 | 2 | 2 | $11.82 | 7 | $12.50 |
| 2015 | 5 | 5 | $20.00 | 20 | $20.65 |
| 2016 | 1 | 1 | $28.00 | 11 | $22.00 |
| 2017 | 2 | 2 | $17.12 | 10 | $17.00 |
| 2018 | 6 | 6 | $28.00 | 16 | $26.50 |
| 2019 | 3 | 3 | $37.00 | 7 | $22.00 |
| 2020 | 1 | 1 | $10.00 | 3 | $10.00 |
| 2022 | 2 | 2 | $14.18 | 5 | $18.00 |
| 2023 | 4 | 4 | $28.09 | 12 | $24.12 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 21 | $18.70 | 84 | $18.00 |
| SCR region | 7 | $15.00 | 32 | $15.50 |
| ER region | 6 | $11.85 | 20 | $10.18 |
| SWR region | 5 | $10.00 | 14 | $12.25 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 20 to 4,850 | 10 | $55.00 |
| 5,095 to 56,197 | 10 | $14.75 |
| 59,911 to 160,276 | 10 | $11.95 |
| 173,510 to 479,032 | 10 | $16.38 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 05 APR 2023 | 009948 | SCR region | 749 | $170.00 | $110.00 | $50.00 | 3 | COMBINED CONSTRUCTION, INC. | WSDOT |
| 08 MAR 2023 | 009942 | NWR region | 10,349 | $27.93 | $24.00 | $20.00 | 3 | PENHALL COMPANY | WSDOT |
| 25 JAN 2023 | 009910 | NWR region | 159,950 | $16.80 | $20.25 | $18.00 | 5 | ACME CONCRETE PAVING, INC. | WSDOT |
| 11 JAN 2023 | 009901 | NWR region | 449,374 | $28.25 | $28.25 | $20.00 | 1 | GARY MERLINO CONSTRUCTION CO., | WSDOT |
| 30 MAR 2022 | 009779 | ER region | 122,020 | $10.35 | $12.18 | $10.00 | 2 | ACME CONCRETE PAVING, INC. | WSDOT |
| 02 MAR 2022 | 009762 | NWR region | 62,630 | $18.00 | $20.00 | $25.00 | 3 | MIDMOUNTAIN CONTRACTORS, INC. | WSDOT |
| 15 JAN 2020 | 009505 | ER region | 4,850 | $10.00 | $10.00 | $25.00 | 3 | SHAMROCK PAVING, INC. | WSDOT |
| 24 APR 2019 | 009428 | ER region | 261,900 | $37.00 | $37.00 | $17.48 | 1 | ACME CONCRETE PAVING, INC. | WSDOT |
| 13 MAR 2019 | 009385 | SCR region | 38,216 | $15.00 | $18.00 | $14.00 | 5 | MAX J. KUNEY COMPANY | WSDOT |
| 06 FEB 2019 | 009361 | NWR region | 480 | $190.00 | $190.00 | $30.00 | 1 | C.A. CAREY CORPORATION | WSDOT |
| 18 APR 2018 | 009253 | OR region | 2,973 | $35.00 | $35.00 | $50.00 | 3 | HAMILTON CONSTRUCTION CO. | WSDOT |
| 04 APR 2018 | 009235 | NWR region | 75,900 | $26.00 | $26.00 | $19.00 | 3 | MIDMOUNTAIN CONTRACTORS, INC. | WSDOT |
| 04 APR 2018 | 009232 | SWR region | 2,084.45 | $30.00 | $30.00 | $25.00 | 1 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 28 MAR 2018 | 009231 | NWR region | 366,375 | $18.70 | $19.85 | $17.00 | 2 | GRAHAM CONTRACTING, LTD. | WSDOT |
| 28 FEB 2018 | 009213 | NWR region | 294,765 | $16.50 | $16.50 | $18.00 | 3 | ACME CONCRETE PAVING, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.