Centerline rumble strip unit price, Washington
Low bidders on WSDOT contracts carried a median of $49,000 per MI for centerline rumble strip, over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 5 bids fell between $43,780 and $49,000.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- MI
- Latest letting
- 07 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2005 | 2 | 2 | $1,012.50 | 6 | $962.50 |
| 2006 | 11 | 11 | $950.00 | 29 | $1,000.00 |
| 2007 | 6 | 6 | $1,075.00 | 15 | $1,050.00 |
| 2008 | 11 | 11 | $1,200.00 | 38 | $1,450.00 |
| 2009 | 7 | 7 | $950.00 | 20 | $950.00 |
| 2010 | 12 | 12 | $987.50 | 51 | $995.00 |
| 2011 | 8 | 8 | $2,475.00 | 44 | $3,225.00 |
| 2012 | 9 | 9 | $1,200.00 | 57 | $3,200.00 |
| 2013 | 8 | 8 | $9,192.50 | 47 | $9,485.00 |
| 2014 | 7 | 7 | $2,400.00 | 46 | $5,000.00 |
| 2015 | 13 | 13 | $2,452.50 | 39 | $1,701.00 |
| 2016 | 12 | 12 | $1,500.00 | 46 | $12,110 |
| 2017 | 13 | 13 | $5,500.00 | 46 | $10,750 |
| 2018 | 16 | 16 | $9,500.00 | 55 | $15,000 |
| 2019 | 17 | 17 | $2,000.00 | 55 | $5,000.00 |
| 2020 | 5 | 5 | $1,920.00 | 15 | $1,400.00 |
| 2021 | 10 | 10 | $1,300.00 | 33 | $1,800.00 |
| 2022 | 13 | 13 | $2,500.00 | 33 | $2,500.00 |
| 2023 | 10 | 10 | $3,575.00 | 40 | $8,875.00 |
| 2026 | 1 | 1 | $49,000 | 5 | $47,000 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 47 | $3,200.00 | 181 | $4,485.58 |
| NCR region | 46 | $1,375.00 | 143 | $2,500.00 |
| OR region | 35 | $2,800.00 | 139 | $5,500.00 |
| ER region | 30 | $1,163.50 | 99 | $1,200.00 |
| SCR region | 24 | $1,445.00 | 98 | $1,500.00 |
| SWR region | 9 | $9,485.00 | 60 | $7,450.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (MI) | Low bids | Low-bid median |
|---|---|---|
| 0.01 to 0.39 | 47 | $24,000 |
| 0.40 to 3.20 | 48 | $2,780.00 |
| 3.25 to 10 | 48 | $1,200.00 |
| 10.40 to 223.23 | 48 | $962.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 07 OCT 2026 | XE3773 | OR region | 0.20 | $49,000 | $47,000 | $25,000 | 5 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 29 MAR 2023 | 009954 | NWR region | 9.46 | $3,400.00 | $3,450.00 | $3,200.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 22 MAR 2023 | 009949 | SCR region | 17.20 | $1,000.00 | $1,100.00 | $2,000.00 | 3 | CENTRAL WASHINGTON ASPHALT, INC.GRANITE CONSTRUCTION COMPANY | WSDOT |
| 08 MAR 2023 | 009937 | NWR region | 0.20 | $23,000 | $23,000 | $34,333 | 3 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 01 MAR 2023 | 009935 | NWR region | 0.02 | $252,475 | $240,000 | $40,000 | 5 | FABER CONSTRUCTION CORP. | WSDOT |
| 23 FEB 2023 | 009934 | NCR region | 12.10 | $1,550.00 | $1,670.00 | $1,500.00 | 3 | CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 01 FEB 2023 | 009928 | OR region | 5.69 | $2,800.00 | $2,762.50 | $2,000.00 | 4 | TUCCI & SONS, INC. | WSDOT |
| 01 FEB 2023 | 009916 | NWR region | 3.50 | $3,750.00 | $3,825.00 | $5,800.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 01 FEB 2023 | 009924 | NWR region | 0.17 | $41,000 | $36,500 | $10,000 | 7 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 25 JAN 2023 | 009914 | ER region | 17.20 | $1,125.00 | $1,520.00 | $1,500.00 | 4 | POE ASPHALT PAVING, INC. | WSDOT |
| 19 JAN 2023 | 009891 | OR region | 0.71 | $9,000.00 | $9,935.00 | $3,781.00 | 7 | CECCANTI, INC. | WSDOT |
| 13 APR 2022 | 009796 | NWR region | 2.50 | $4,485.58 | $4,992.79 | $5,350.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 06 APR 2022 | 009791 | ER region | 8.80 | $2,400.00 | $2,075.00 | $1,500.00 | 2 | INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 30 MAR 2022 | 009778 | NCR region | 8.10 | $2,500.00 | $2,670.00 | $1,350.00 | 3 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 30 MAR 2022 | 009779 | ER region | 8.30 | $2,615.00 | $2,557.50 | $800.00 | 2 | ACME CONCRETE PAVING, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.