Channel excavation incl. haul unit price, Washington
Low bidders on WSDOT contracts carried a median of $21.23 per CY for channel excavation incl. haul, over the 24 months to 07 OCT 2026, across 2 low bids. Half of all 13 bids fell between $65.00 and $113.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- CY
- Latest letting
- 23 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2003 | 1 | 1 | $25.00 | 5 | $25.00 |
| 2005 | 1 | 1 | $14.21 | 4 | $15.86 |
| 2008 | 2 | 2 | $37.50 | 17 | $41.00 |
| 2010 | 4 | 4 | $8.20 | 46 | $9.75 |
| 2011 | 4 | 4 | $11.70 | 41 | $17.00 |
| 2012 | 3 | 3 | $15.00 | 23 | $20.00 |
| 2013 | 2 | 2 | $15.00 | 13 | $20.00 |
| 2014 | 3 | 3 | $32.50 | 21 | $18.50 |
| 2015 | 4 | 4 | $26.70 | 29 | $45.00 |
| 2016 | 8 | 8 | $20.50 | 63 | $25.00 |
| 2017 | 3 | 3 | $30.00 | 19 | $25.00 |
| 2019 | 4 | 4 | $28.50 | 17 | $34.00 |
| 2020 | 4 | 4 | $35.00 | 22 | $39.50 |
| 2021 | 1 | 1 | $36.00 | 6 | $42.00 |
| 2022 | 2 | 2 | $38.50 | 5 | $50.00 |
| 2023 | 3 | 3 | $27.10 | 10 | $42.00 |
| 2026 | 2 | 2 | $21.23 | 13 | $95.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 27 | $26.33 | 206 | $26.00 |
| OR region | 8 | $21.50 | 50 | $28.00 |
| SCR region | 6 | $74.00 | 43 | $28.00 |
| SWR region | 5 | $15.30 | 35 | $14.00 |
| ER region | 4 | $16.25 | 17 | $20.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 6 to 136 | 12 | $34.50 |
| 140 to 538 | 13 | $23.00 |
| 640 to 2,260 | 13 | $30.00 |
| 3,606 to 54,550 | 13 | $14.21 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 23 SEP 2026 | XE3772 | SCR region | 30 | $14.45 | $97.00 | n/a | 8 | SCARSELLA BROS., INC. | WSDOT |
| 15 JUL 2026 | XE3755 | SCR region | 19 | $28.00 | $70.00 | $75.00 | 5 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 08 MAR 2023 | 009937 | NWR region | 21,470 | $27.10 | $25.00 | $22.25 | 3 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 01 MAR 2023 | 009935 | NWR region | 410 | $38.00 | $70.00 | $40.00 | 5 | FABER CONSTRUCTION CORP. | WSDOT |
| 23 FEB 2023 | 009925 | ER region | 7,400 | $13.00 | $39.00 | $12.00 | 2 | MAX J. KUNEY COMPANY | WSDOT |
| 09 MAR 2022 | 009774 | OR region | 8,380 | $25.00 | $31.50 | $35.00 | 2 | KRAEMER NORTH AMERICA, LLC. | WSDOT |
| 20 JAN 2022 | 009754 | NWR region | 640 | $52.00 | $52.00 | $20.00 | 3 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 21 APR 2021 | 009672 | NWR region | 150 | $36.00 | $42.00 | $20.00 | 6 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 01 APR 2020 | 009533 | SCR region | 6 | $200.00 | $195.00 | $140.00 | 5 | KRCI LLC | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 54,550 | $8.50 | $26.00 | $29.00 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 20 FEB 2020 | 009523 | NWR region | 100 | $25.00 | $52.00 | $20.00 | 5 | STRIDER CONSTRUCTION CO., INC. | WSDOT |
| 23 JAN 2020 | 009509 | ER region | 1,220 | $45.00 | $35.00 | $30.00 | 4 | GARCO CONSTRUCTION, INC. | WSDOT |
| 24 APR 2019 | 009426 | ER region | 8,540 | $17.50 | $18.25 | $11.00 | 4 | N.A. DEGERSTROM, INC. | WSDOT |
| 27 MAR 2019 | 009399 | NCR region | 17,471 | $27.00 | $27.00 | $15.00 | 3 | STRIDER CONSTRUCTION CO., INC. | WSDOT |
| 13 MAR 2019 | 009374 | NWR region | 1,720 | $30.00 | $54.00 | $20.00 | 7 | MARSHBANK CONSTRUCTION, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.